3.8TOP EXIT HORIZONTAL TERMINATION

(HT) > (VT)

Simple venting configuration (only one 90° elbow)

See graph to determine the required vertical rise VT for the

required horizontal run HT.

147”

150

FIGURE 3.8a

REQUIRED

100

 

 

 

 

 

 

 

 

 

VERTICAL

 

 

 

 

 

RISE IN

 

 

 

 

 

INCHES VT

57”

 

 

 

 

 

 

 

 

 

 

50

 

 

 

 

 

19 1/2”

 

 

 

 

 

0

5

10

15

20

 

 

2’

 

12.5’

19.5’

HORIZONTAL VENT RUN PLUS OFFSET IN FEET HT

 

 

 

 

 

 

 

 

 

The shaded area within the lines represents acceptable

 

 

 

 

 

 

 

 

 

 

values for HT and VT

For vent configurations requiring more than one 90° elbow, the following formulas apply:

 

 

Formula 1: HT

< 4.2 VT

 

 

 

 

 

Formula 2: HT

+ VT < 24.75 feet

 

90°

 

H1

H2

 

 

 

 

 

 

 

 

 

 

Example 2:

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

V1

= VT = 6 FT

 

 

FIGURE 3.8b

 

 

90°

 

H1

= 3 FT

 

 

 

 

V1

 

 

 

 

 

 

 

 

 

 

H2

= 5 FT

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

HR

= H1

+ H2

= 3 + 5 = 8 FT

 

 

 

 

 

HO

= .03 (two 90° elbows - 90°) = .03 (180° - 90°) = 2.7 FT

 

 

 

 

HT

= HR

+ HO

= 8 + 2.7 = 10.7 FT

 

 

 

 

 

HT

+ VT

= 10.7 + 6 = 16.7 FT

 

 

 

 

 

Formula 1:

 

H

< 4.2 V

 

 

 

 

 

Formula 2:

 

T

4.2 VTT = 4.2 x 6 = 25.2 FT

 

 

 

 

 

HT

+ VT < 24.75 FT

 

 

 

 

90°

 

 

 

 

 

 

16.7 < 24.75

 

 

 

90°

Since both formulas are met, this vent configuration is acceptable.

90°

H

H4

Example 3:

 

 

 

 

 

1

V2

 

 

 

 

 

 

H2

 

 

 

 

 

 

H3

V1

= 4 FT

 

 

 

 

 

 

 

V2

= 1.5 FT

= 4 + 1.5 = 5.5 FT

FIGURE 3.8c

V1

90°

 

V

T

= V + V

2

 

 

 

 

 

1

 

 

 

 

 

 

 

 

 

H1

= 2 FT

 

 

 

 

 

 

 

 

 

H2

= 1 FT

 

 

 

 

 

 

 

 

 

H3

= 1 FT

 

 

 

 

 

 

 

 

 

H4

= 1.5 FT

+ H3 + H4 = 2 + 1 + 1 + 1.5 = 5.5 FT

 

 

 

 

HR

= H1

+ H2

 

 

 

 

HO

= .03 (four 90° elbows - 90°) = .03 (360° - 90°) = 8.1 FT

 

 

 

 

HT

= HR

+ HO

= 5.5 + 8.1 = 13.6 FT

 

 

 

 

 

HT

+ VT

= 13.6 + 5.5 = 19.1 FT

 

 

 

 

 

Formula 1:

 

HT

< 4.2 VT

 

 

 

 

 

 

 

 

 

 

 

 

4.2 VT = 4.2 x 5.5 = 23.1 FT

 

 

 

 

 

 

 

 

 

 

13.6 < 23.1

 

 

 

 

 

Formula 2:

 

HT

+ VT < 24.75 FT

 

 

 

 

 

 

 

 

 

 

 

19.1 < 24.75

 

 

 

 

 

Since both formulas are met, this vent configuration is acceptable.

16.1_2

W415-0788 / A / 09.22.09

Image 17
Contents GDS60N & GS60N Table of Contents Installation Installation OverviewIntroduction General Instructions DimensionsGeneral Information We suggest that our gasModel Natural GAS/GAZ Natural Rating PlateShipping Bracket Care of GlassGlass Door Removal Shippingbracket LatchVenting Model GDS60 Refer to the section applicable to your installationPart Supplier Website Venting Lengths and ComponentsTOP Vent Minimum Feet Maximum Rear Vent Typical Vent InstallationsMinimum Feet Maximum Minimum Plus Rise PlusRise Corner Termination Special Vent Installations 3.3.1 Periscope TerminationGrade To Grade MinimumVent Terminal Clearances Installations CanadaRear Exit Venting Application Flow Chart TOP ExitFeet Inches DefinitionsElbow Vent Length Values HT VT TOP Exit Horizontal TerminationFormula 1 HT VT Formula 2 HT + VT 40 FT Horizontal Vent RUN Plus Offset in Feet HT Rear Exit Horizontal Termination10c 11a TOP or Rear Exit Vertical Termination11c Rear Vent Termination Installation Preparation Model GDS60Orifice Replacement Changing a TOP Vent to a Rear Vent Maintain These Minimum Clearances to Combustibles InstallationMinimum Clearance to Combustibles Wall and Ceiling Protection Horizontal InstallationHorizontal AIR Terminal Installation Model GDS60 Vertical InstallationHigh Temperature Sealant Inner Flex Pipe Vertical AIR Terminal Installation Model GDS60Roof Support Inner PipeGAS Installation Mobile Home Installation Model GDS60High Temperature Sealant Appliance Vent Connection Model GDS60Wire Size MAX. Length Optional Wall Switch / ThermostatVent Specifics Model GS60 5.7.1 Chimney Installation Combustion AIR Installing B VentMore MIN Flat Roof Wall Adding Vent SectionsCaulking Storm Collar Weather Sealant Flashing Installing Flashing and Storm CollarFinishing Glass Door Installation and RemovalFront Cast Removal Return FlangeLOG Placement Glass / Door ReplacementLogo Placement Access Cover Plate Switch and Bracket InstallationSlot Removed Screws Optional Blower InstallationWiring Diagram Model GS60 only Venting Action Check OperationOperating Instructions Lighting Instructions Anti Condensation SwitchPilot Burner Adjustment AdjustmentVenturi Adjustment Flame CharacteristicsMaintenance Common Components ReplacementsGS60 Components Roof Terminal Kits 49 50 Symptom Problem Trouble ShootingSymptom Problem Test Solution GDS600 only HOTGlass Embers only GS600 onlyConditions and Limitations WarrantyAppliance Service History Service History