10" (25.4 cm)

INTERIOR

WALL SHIELD

12" (30.5 cm)

Figure 18. Flue Pipe & Firestop

For Vertical Runs - One firestop is REQUIRED at the hole in each ceiling through which the flue passes.

To install firestops for vertical runs that pass through ceilings:

Position a plumb bob directly over the center of the verti- cal flue component.

Mark the ceiling to establish the center point of the flue.

Drill a hole or drive a nail through this center point.

Check the floor above for any obstructions, such as wir- ing or plumbing runs.

Reposition the heater and flue system, if necessary, to accommodate the ceiling joists and/or obstructions.

Cut a 25.4 cm X 30.5 cm hole through the ceiling, using the firestop pipe opening as a guide.

Frame the hole with framing lumber the same size as the ceiling joists.

10" (25.4 cm)

10” (25.4 cm)

 

 

CHIMNEY

 

HOLE

NEW

EXISTING CEILING

JOISTS

FRAMING

 

MEMBERS

 

CEILING

 

Figure 19. Hole and New Framing Members

Heat & Glo • 6000TRS-CE2049-900 Rev. Q • 2/11

23

Image 23
Contents What to do if you smell gas ModelSafety and Warning Information Maintaining and Servicing Installing the FireplaceService Parts Log Set Assembly6000TRS-CE Service Parts List6000TRS-CE Valve AssemblyAppliance Certification Installation RegulationsANY Such Action MAY Possibly Cause a Fire Hazard Location Centimeters Clearance Requirements StepLocating FireplaceFraming should be constructed of 2 X 4 lumber or heavier Step Framing FireplaceIdentifying Flue Components Step Installing Flue SystemFlue System Approvals DVP4 DVP6 DVP12 Straight UP Flue with ONE 1 90o Elbow Flue with TWO 2 90 Elbows Flue with TWO 2 90 Elbows Flue with Three 3 90 Elbows + H Venting Out the Top Flue Installing Flue ComponentsVenting Out the Rear Flue On the TOP of the heater Install Support BracketsInstalling Support Brackets Install FirestopsFlue Pipe & Firestop Flue Termination For Horizontal Terminations using the DVP-TRAPBe Positioned SO That the Arrow is Pointing UP DVP Termination Cap Outside of the building Alcove Applications Standing Pilot Ignition System Step Positioning Leveling, Securing FireplaceStep Gas Supply Line Step Gas Pressure Requirements Optional AccessoriesFinishing Fractory Installing the TrimInstalling the Ceramic Re LOG Placement Heat & Glo 6000TRS-CE 2049-900 Rev. Q 2/11 Placing the Ember Material Glass AssemblyDouble-check for gas leaks Review safety warnings and cautionsDouble-check for faulty components Step Before Lighting FireplaceStep Lighting Fireplace After the Installation Maintaining Servicing Your Fireplace Make Sure the Flames Standing Pilot Troubleshooting With the pilot lit, and the ON/OFF switch Placed in this Opening Limited Lifetime Warranty Limited Lifetime WarrantyWarranty Conditions