For Vertical Terminations - To locate the flue and install the flue sections:

Locate and mark the flue center point on the underside of the roof, and drive a nail through the center point.

Make the outline of the roof hole around the center point nail.

The size of the roof hole framing dimensions depend on the pitch of the roof. There MUST BE a 2.5 cm clearance from the vertical flue pipe to combustible materials.

Mark the roof hole accordingly.

Cover the opening of the installed flue pipes.

Cut and frame the roof hole.

Use framing lumber the same size as the roof rafters and install the frame securely. Flashing anchored to the frame must withstand heavy winds.

Continue to install concentric flue sections up through the roof hole and up past the roof line until you reach the appropriate distance above the roof.

To seal the roof hole, and to divert rain and snow from the flue system:

Attach a flashing to the roof using nails, and use a non- hardening mastic around the edges of the flashing base where it meets the roof.

Attach a storm collar over the flashing joint to form a water-tight seal. Place non-hardening mastic around the joint, between the storm collar and the vertical pipe.

Slide the termination cap over the end of the flue pipe and snap into place.

26

Heat & Glo • 6000TRS-CE2049-900 Rev. Q • 2/11

Image 26
Contents Model What to do if you smell gasSafety and Warning Information Installing the Fireplace Maintaining and ServicingLog Set Assembly Service PartsService Parts List 6000TRS-CEValve Assembly 6000TRS-CEInstallation Regulations Appliance CertificationANY Such Action MAY Possibly Cause a Fire Hazard Location Centimeters Fireplace StepLocating Clearance RequirementsStep Framing Fireplace Framing should be constructed of 2 X 4 lumber or heavierIdentifying Flue Components Step Installing Flue SystemFlue System Approvals DVP4 DVP6 DVP12 Straight UP Flue with ONE 1 90o Elbow Flue with TWO 2 90 Elbows Flue with TWO 2 90 Elbows Flue with Three 3 90 Elbows + H Venting Out the Top Flue Installing Flue ComponentsVenting Out the Rear Flue Install Support Brackets On the TOP of the heaterInstall Firestops Installing Support BracketsFlue Pipe & Firestop For Horizontal Terminations using the DVP-TRAP Flue TerminationBe Positioned SO That the Arrow is Pointing UP DVP Termination Cap Outside of the building Alcove Applications Step Positioning Leveling, Securing Fireplace Standing Pilot Ignition SystemStep Gas Supply Line Optional Accessories Step Gas Pressure RequirementsFinishing Fractory Installing the TrimInstalling the Ceramic Re LOG Placement Heat & Glo 6000TRS-CE 2049-900 Rev. Q 2/11 Glass Assembly Placing the Ember MaterialStep Before Lighting Fireplace Review safety warnings and cautionsDouble-check for faulty components Double-check for gas leaksStep Lighting Fireplace After the Installation Maintaining Servicing Your Fireplace Make Sure the Flames Standing Pilot Troubleshooting With the pilot lit, and the ON/OFF switch Placed in this Opening Limited Lifetime Warranty Limited Lifetime WarrantyWarranty Conditions