Design Dynamics DVF-36S-N Vertical Termination Installation, Flat Ceiling Installation

Page 12

Venting Installation

Continued

Vertical Termination Installation

Note: Vertical restrictor must be installed in all vertical installations.

1.Determine the route your vertical venting will take. If ceiling joists, roof rafters or other framing will obstruct the venting system, consider an offset (see Figure 16) to avoid cutting load bearing members. Note: Pay special attention to these instal- lation instructions for required clearances (air space) to combustibles when passing through ceilings, walls, roofs, enclosures, attic rafters, etc. Do not pack air spaces with insulation. Also note maximum verti- cal rise of the venting system and any maximum horizontal offset limitations.

2.Set the fireplace in desired location. Drop a plumb line down from the ceiling to the position of the fireplace exit flue. Mark the center point where the vent will penetrate the ceiling. Drill a small locating hole at this point.

Drop a plumb line from the inside of the roof to the locating hole in the ceiling. Mark the center point where the vent will penetrate the roof. Drill a small locating hole at this point.

Roof Flashing

Wall Strap

Flat Ceiling Installation

1.Cut a 11 1/2" square hole in the ceiling using the locating hole as a center point.

The opening should be framed to 11 1/2" x 11 1/2" inside dimensions, as shown in Figure 8 on page 9 using framing lumber the same size as the ceiling joists. If the area above the ceiling is an insulated ceiling or an attic, nail firestop from the top side. This prevents loose insulation from falling into the required clearance space. Of the area above the ceiling is a living space, install firestop below the framed hole. The firestop should be installed with no less than three nails per side (see Figure 17).

2.Assemble the desired lengths of pipe and elbows necessary to reach from the fireplace flue up through the firestop. Be sure all pipe and elbow connections are fully twist-locked (see Figure 7, page 9).

3.Cut a hole in the roof using the locating hole as a center point. (Cover any exposed open vent pipes before cutting hole in roof.)

The 11 1/2" x 11 1/2" hole must be measured on the horizontal; actual length may be larger depending on the pitch of the roof. There must be a 1" clearance from the vent pipe to combustible materials. Frame the opening as shown in Figure 9, page 9.

4.Connect a section of pipe and extend up through the hole.

Note: If an offset is needed to avoid obstructions, you must support the vent pipe every 3 feet. Use wall straps for this purpose (see Figure 15, page 11). When- ever possible, use 45° elbows instead of 90° elbows. The 45° elbow offers less restriction to the flow of the flue gases.

If area above is an attic or insulated area, install firestop above framed hole.

45° Elbow

If area above is a living space, install firestop below framed hole.

Ceiling Firestop

Figure 16 - Offset with Wall Strap and 45°

Elbows

Figure 17 - Installing Firestop

12

www.desatech.com

120441-01A

Image 12
Contents Natural Propane/LP Gas Models Gas ModelsStacked Brick/Standard Glass Table of Contents Safety InformationNatural and Propane/LP Gas Natural This fireplaceProduct Features Product IdentificationLocal Codes Preinstallation InstallationLocation and space requirements Proper clearances must be maintainedClearances Framing and finishingFor specific venting ClearancesLocation of Termination Cap Balcony with Perpendicular Side WallVenting Installation Installation PrecautionsInstallation Planning Twist-Lock Procedure The femaleApply Mastic to All Four Sides Vent Cap Wood Screw See ,To All Four Sides Elbow Wall Firestop Horizontal High Wind Square TerminationMax max max Vertical Termination Installation Flat Ceiling InstallationOutside Air Flex Installation High Altitude InstallationVertical Venting = 40 maxFireplace Installation Parts list for venting kits and componentsInstalling Gas Piping to Fireplace Location Check GAS TypeGas Connection Connecting Fireplace to GAS Supply Checking GAS ConnectionsPsig 3.5 kPa will damage fireplace gas regulator Test Pressures Equal To or Less Than 1/2 Psig 3.5 kPaPressure Testing Fireplace Gas Connections Installing Middle Door DVF-36SC/HC Models OnlyInstalling Outer Door DVF-36SC/HC Models Only FireplaceSee , Follow these instructions in reverse to reinstall Spring Loaded Pin Pin Located on Middle DoorHook LocatedOuter Door Hinge On Inner Door Middle Door Remove screen and rod see ,Lava Rock, Ember Flakes Scrap Log Installation Side Bricks Side Trim Screen Rod LeftBottom Brick Middle Bottom Brick Right Bottom BrickWall Switch Installation Remote control Installation Model WRCWiring Diagram For your safety Read before lightingOperation Lighting InstructionsPilot Assembly Inspecting BurnersTo Turn OFF GAS To Appliance Remote OperationCleaning Maintenance Glass DoorsTechnical Service SpecificationsReplacement Parts Service HintsTroubleshooting Observed Problem Possible Cause Remedy21 and/or check ground wire to ignition module Pilot will not stay litTo ignition module and/or Poor ground to ignitionConfiguration Tions,Glass soots Debris around burner air Illustrated Parts Breakdown Parts List Not a field replaceable partIllustrated parts breakdown Bottom Pan Weldment Illustrated parts breakdown 120168-01 Refractory Trim, RH 120168-02 Refractory Trim, LH 120441-01A 120441-01A Warranty Information Keep this WarrantyLimited Warranty Direct vent Fireplace