Vermont Casting BHDR36 installation instructions Vertical Through the Roof Installation

Page 25

VERTICAL THROUGH THE ROOF INSTALLATION

1.Locate your fireplace.

2.Plumb to centre of the (4") 90o transition elbow (7TDVRT90) from ceiling above and mark position.

3.Cut opening equal to 9-3/8" x 9-3/8" (240 mm x 240 mm).

4.Proceed to plumb for additional openings through the roof. In all cases, the opening must provide a minimum of 1 inch clearance to the vent pipe, i.e., the hole must be at least 9-3/8" x 9-3/8" (240 mm x 240 mm).

5.Place fireplace into position and secure to floor.

6.Place firestop(s) 7DVFS into position and secure. (Fig. 63)

7.Install roof support (Fig. 36) and roof flashing making sure upper flange of flashing is below the shingles. (Fig. 64)

8.Install appropriate pipe sections until above the flash- ing. (See Fig. 62 for #'s 7, 8 and 9).

9.Install storm collar and seal around the pipe.

10.Add additional vent lengths for proper height. (Fig. 62)

Attic

 

 

Insulation

 

 

Shield

11"

 

 

 

JOIST

 

 

Fig. 63

Ceiling

11"

UPPER FLOOR

Installation

 

 

 

 

 

JOIST

 

 

FIRESTOP

 

 

SPACER

 

 

NAILS (4)

Fig. 63 If there is a room above ceiling level, firestop spacer must be installed on both the bottom and the top side of the ceiling joists. If an attic is above ceiling level a 7DVAIS (Attic Insulation Shield) must be installed.

Fig. 64 The enlarged ends of the vent section always face downward.

Fig. 64

SHEETMETAL SCREWS (#5) Ñ

3 PER JOINT

SEALANT

STORM COLLAR

- 25 -

Image 25 Contents
BHDR36 Table of Contents Locating Your GAS Fireplace Installation InstructionsFireplace Dimensions Mantels Mantel ChartClearance to Combustibles Framing and FinishingFinal Finishing GAS SpecificationsHearth Remote Switch Installation For RN/RP GAS Line InstallationGeneral Venting Information Termination Clearances Rear Venting Applications Rear Wall InstallationsVertical Sidewall Installations Vertical Sidewall Applications Vent Sidewall Installation HOW to USE the Vent GraphSidewall Venting Graph Ensure Pipes Are Vertical Through Roof Applications Below Grade InstallationsProceed to plumb for additional openings through Vertical Thru Roof InstallationCrimped END Venting Components Rear Venting Applications General Information on Assembling Twist Lock Vent Pipes190mm Vertical Sidewall Applications Vertical Sidewall InstallationsSee page 23 for Venting Requirements for Snorkels NON-COMBUSTIBLE Walls Hole opening must be Installation Below Grade InstallationsRise Vertical Through Roof ApplicationsVertical Through the Roof Installation Twist Lock Venting Components General Glass Information Glass CleaningLouvre Removal Glass Frame RemovalFlame Adjustment Installation of LogsLava Rock Maintenance Flame CharacteristicsCleaning the Standing Pilot Control System Inspecting the Venting SystemLighting and Operating Instructions Trouble Shooting the GAS Control System SIT 820 Nova Millivolt Valve Replacement Parts List Replacement Parts Optional BAY Window Installation Wiring InstructionsOptional FAN KIT FK24 Optional Ceramic Refractory Installation Optional Screen KIT InstallationOptional Remote Control