Weil-McLain 550-110-260/0107 manual Burners, base and inlet air box, Condensate drain system

Page 39

GOLD CGs Gas-Fired Water Boiler — Boiler Manual

Inspect . . .

Burners, base and inlet air box

The boiler contains ceramic fiber and fiberglass materials. Use care when handling these materials per instructions on page 68 of this manual. Failure to comply could result in severe personal injury.

If insulation is damaged or displaced, do not operate the boiler. Replace or reposition insulation as neces- sary. Failure to replace damaged insulation can result in a fire hazard, causing severe personal injury, death or substantial property damage.

1.After turning off power to the boiler, remove the inlet air box top panel (Figure 27, item 13, page 56).

2.Inspect gasket (item 14). Replace if necessary.

3.Inspect burners and all other components in the inlet air box and boiler base.

4.If burners must be cleaned, first remove item 11, Figure 27, page 56. Access the burner assembly by first removing burner baffle, item 4. Then remove the screws securing the burner tray to the manifold. Slide the burner tray out. Follow Burner cleaning instructions below to clean burners thoroughly.

6.Inspect the base insulation. Pay attention to the WARNING on page 64 regarding working with insulation materials. Verify that the insulation is intact and secure against all four sides of the base.

7.Replace all components when service has been completed.

Burner cleaning instructions

Airborne materials, such as fiberglass and dust, are pres- ent during construction and remodeling. These materi- als can be drawn in with the combustion air and obstruct burner ports, resulting in carbon monoxide production, a fire hazard, or building freeze damage. Read and follow the WARNING on page 9. Failure to inspect and clear gas burner ports could result in severe personal injury, death or substantial property damage.

1.Inspect each burner to insure that every port is completely open.

2.If any port is not completely clear, run a vacuum at the burner inlet while cleaning the burner ports with a wire brush. The vacuum will help to draw any airborne material out of the burner.

3.Follow instructions above to replace all components after cleaning.

Condensate drain system

1.Inspect condensate drain fittings and tubing. Verify that condensate can flow freely to drain.

Service . . .

Inducer motor

1.With boiler power off, place a few drops of S.A.E. 20 motor oil in each of the two oil cups.

Use only S.A.E. 20 motor oil to lubricate the inducer motor. Do not use universal household oils. Motor could be damaged, resulting in pos- sible severe property damage.

Oiled-bearing circulators

1.The circulator shipped with the CGs boiler is water- lubricated. No oiling is required.

2.Check other circulators in the system. Oil any circulators requiring oil, following circulator man- ufacturer’s instructions. Over-oiling will damage the circulator.

Start-up . . .

1.Perform all start-up procedures in Section 7 of this manual.

2.Verify cold fill pressure is correct and that fill system is working properly.

3.Verify antifreeze level (if used) is at the right con- centration and that inhibitor level is correct.

4.Check gas piping, per manual Sections 5 and 7, verifying no indications of leakage and all piping and connections are in good condition.

5.Read the Operating instructions (Section 9c of this manual or on boiler label) applying to the boiler.

6.Start the boiler following the Operating instruc- tions (Section 9c of this manual or on boiler label) and manual Section 7.

Part number 550-110-260/0107

39

Image 39
Contents Gold CGs How it works Gold CGs Gas-Fired Induced-Draft Water Boiler Contents Installer Please read before proceedingUser 1a Prepare boiler location codes & checklist Installations must follow these codesBefore locating the boiler, check the following 1b Prepare boiler location clearances Vent system When removing boiler from an existing common vent system1c Prepare boiler location vent system CGs special vent systemProducts to avoid 1d Prepare boiler location contaminationSizing air openings 1e Prepare boiler location air openingsCombustion air options Special considerationsSizing air openings for CGs installations Inspect orifices and burners 2a Prepare boiler placement & setupOrifice replacement procedure Place boiler/crate near positionPrepare boiler for test 2b Prepare boiler pressure testHydrostatic pressure test Drain and remove fittings3a Water piping general information 3b Water piping single-zone system Systems 3c Water piping multiple zonesPiping multiple zones Piping for radiant heating Systems or converted gravityReturn water 130F or higher Primary/secondary preferred bypass piping method Temperature gaugesValve adjustment Figures 8 and 9 only 3d Piping low temp systemsPrimary/secondary piping BOILER-bypass piping method Valve adjustmentFigures 8 SYSTEM-bypass piping method Prevent chilled water from entering 3e Water piping refrigeration systemsVenting and combustion air Propane Gas Connecting gas supply piping to boilerGas piping Natural GasThermostat Field wiringElectrical installation must comply with Wiring connectionsVerify water chemistry Freeze protection when used7a Start-up preparation Check for gas leaksStart the boiler 7b Start-up operate boilerInspect system water piping Inspect base insulation Final check before starting boilerPilot burner flame Figure 7c Start-up if boiler doesn’t startCheck burner flames Check forInstallation and service certificate Check-out procedure checklist9a Operation sequence Schematic wiring diagram 9b Operation wiring diagramsLadder wiring diagram 9c Operating instructions CGs-3 to CGs-6 9c Operating instructions CGs-3 to CGs-6 9c Operating instructions CGs-3 to CGi-6 Verify Proper Operation After Servicing 10a Service and maintenance schedule10b Service & maintenance annual start-up Oiled-bearing circulators Burners, base and inlet air boxCondensate drain system Inducer motor10b Service & maint. annual start-up Relief valve, typical Boiler relief valveReview with owner Cleaning boiler heating surfaces11a Troubleshooting procedure Before troubleshootingCheck the following Troubleshooting air pressure reading 11b Troubleshooting air pressure switchAir pressure switch Check pressure switch settingTroubleshooting the control module 11c Troubleshooting control moduleControl indicator lights Lockout modes Control indicator lights NON-LOCKOUT modesControl module connections Chart 1 Troubleshooting Power light status 11d Troubleshooting control module lightsChart 2 Tstat Circ & Power lights flashing Chart 3 Press Switch & Power lights flashing Chart 4 Flame & Power lights flashing Item 8 , Does blower motor operate? Verify Sequence of operation, , Section assembly Base Jacket Trim Controls 12a Replacement partsSection assembly 12b Replacement parts section assemblyBase assembly 12c Replacement parts baseDescription Weil-McLain Part number Jacket assembly 12d Replacement parts jacketBoiler Model Weil-McLain part number Part number 12e Replacement parts trimPropane gas components 12f Replacement parts controlsDimensional drawing 13a DimensionsDOE 13b RatingsRemoval of Combustion Chamber Lining or Base Panels Handling ceramic fiber and fiberglass materials