Weil-McLain 550-110-260/0107 manual Venting and combustion air

Page 24

GOLD CGs Gas-Fired Water Boiler — Boiler Manual

4 Venting and combustion air

Install vent piping and air piping (if used) per appropriate Venting Supple- ment included in boiler envelope assembly.

Refer to Venting Supplements and to manual Section 1 regarding require- ments for:

vent system

combustion air openings

combustion air quality

CGs Boiler must be vented and supplied with combus- tion and ventilation air as described in Weil-McLain CGs Venting Supplements packed in envelope as- sembly with boiler. Failure to do so will cause severe personal injury or death.

Use direct vent (sealed combustion) if combustion air quality cannot be assured to be free of contaminants.

Refer to page 9 for a list of potential contaminants and locations likely to contain them. Operating the boiler with contaminated air will damage the boiler sections and vent, resulting in possible boiler failure or leakage of flue products, causing severe personal injury, death or substantial property damage.

24

Part number 550-110-260/0107

Image 24
Contents Gold CGs How it works Gold CGs Gas-Fired Induced-Draft Water Boiler Contents Installer Please read before proceedingUser 1a Prepare boiler location codes & checklist Installations must follow these codesBefore locating the boiler, check the following 1b Prepare boiler location clearances When removing boiler from an existing common vent system 1c Prepare boiler location vent systemCGs special vent system Vent system1d Prepare boiler location contamination Products to avoid1e Prepare boiler location air openings Combustion air optionsSpecial considerations Sizing air openingsSizing air openings for CGs installations 2a Prepare boiler placement & setup Orifice replacement procedurePlace boiler/crate near position Inspect orifices and burners2b Prepare boiler pressure test Hydrostatic pressure testDrain and remove fittings Prepare boiler for test3a Water piping general information 3b Water piping single-zone system 3c Water piping multiple zones Piping multiple zones Piping for radiant heatingSystems or converted gravity SystemsReturn water 130F or higher Temperature gauges Valve adjustment Figures 8 and 9 only3d Piping low temp systems Primary/secondary preferred bypass piping methodPrimary/secondary piping Valve adjustment BOILER-bypass piping methodFigures 8 SYSTEM-bypass piping method 3e Water piping refrigeration systems Prevent chilled water from enteringVenting and combustion air Connecting gas supply piping to boiler Gas pipingNatural Gas Propane GasField wiring Electrical installation must comply withWiring connections ThermostatFreeze protection when used 7a Start-up preparationCheck for gas leaks Verify water chemistry7b Start-up operate boiler Inspect system water piping Inspect base insulationFinal check before starting boiler Start the boiler7c Start-up if boiler doesn’t start Check burner flamesCheck for Pilot burner flame FigureCheck-out procedure checklist Installation and service certificate9a Operation sequence 9b Operation wiring diagrams Schematic wiring diagramLadder wiring diagram 9c Operating instructions CGs-3 to CGs-6 9c Operating instructions CGs-3 to CGs-6 9c Operating instructions CGs-3 to CGi-6 10a Service and maintenance schedule Verify Proper Operation After Servicing10b Service & maintenance annual start-up Burners, base and inlet air box Condensate drain systemInducer motor Oiled-bearing circulators10b Service & maint. annual start-up Boiler relief valve Relief valve, typicalCleaning boiler heating surfaces Review with owner11a Troubleshooting procedure Before troubleshootingCheck the following 11b Troubleshooting air pressure switch Air pressure switchCheck pressure switch setting Troubleshooting air pressure reading11c Troubleshooting control module Control indicator lights Lockout modesControl indicator lights NON-LOCKOUT modes Troubleshooting the control moduleControl module connections 11d Troubleshooting control module lights Chart 1 Troubleshooting Power light statusChart 2 Tstat Circ & Power lights flashing Chart 3 Press Switch & Power lights flashing Chart 4 Flame & Power lights flashing Item 8 , Does blower motor operate? Verify Sequence of operation, , 12a Replacement parts Section assembly Base Jacket Trim Controls12b Replacement parts section assembly Section assembly12c Replacement parts base Base assemblyDescription Weil-McLain Part number 12d Replacement parts jacket Jacket assemblyBoiler Model Weil-McLain part number 12e Replacement parts trim Part number12f Replacement parts controls Propane gas components13a Dimensions Dimensional drawing13b Ratings DOEHandling ceramic fiber and fiberglass materials Removal of Combustion Chamber Lining or Base Panels