GOLD CGs Gas-Fired Water Boiler — Boiler Manual

3d Piping — low temp systems (continued)

SYSTEM-bypass piping method

This piping method (Figure 12, page 23) is called a sys- tem-bypassbecause part of the circulator flow bypasses the system (through valve 7a). This bypassed hot water from the boiler outlet mixes with cooler system return water temperature in order to provide minimum 130°F return water to the boiler. Valve 7b will most often be full open, but may need to be slightly closed on some low pressure drop systems in order to cause enough flow through valve 7a.

Figure 12 is an alternative piping method that provides return water temperature control for boilers installed on converted gravity systems (large water content or steam systems).

Do not apply the piping of Figure 12 on radiant heat- ing systems. It provides no method regulating the water temperature provided to the system and could result in excessive water temperature in the radiant tubing.

System-bypass piping as shown in Figure 12 can be used with either zone valve or circulator zoning. When used with circulator zoning however, the boiler circulator

(item 3), must be piped as shown. It cannot be used as one of the zoning circulators.

Do not apply system-bypass piping if the reduced flow in the system could cause poor heat distribution. That is, system-bypass piping reduces the flow in the system and increases the water temperature supplied to the system. This can cause increased heat from radiators at the beginning of the system and reduced heat from radiators near the end of the system.

Valve adjustment

1.Start with valve 7a fully closed and 7b fully open.

2.Gradually open valve 7a while closing valve 7b until the temperature at gauge 8 reads at least 130°F at all times.

3.Valve 7a regulates the amount of boiler supply water mixed with return water. Valve 7b causes a pressure drop in the system needed to balance flow through valve 7a and the system.

4.The valve adjustment should be done with the system at the coldest expected temperature (60°F for converted gravity systems or high mass radiant systems).

Failure to prevent low return water temperature to the boiler could cause corrosion of the boiler sections or burners, resulting in severe personal injury, death or substantial property damage.

Radiant heating system piping should include a means of regulating the boiler return water temperature and the system supply temperature (such as provided by an injec- tion pumping control).

Boiler return water temperature will be adequately controlled using the methods shown in this manual provided the system supply temperature is relatively constant.

DO NOT apply the methods of this manual if the system is equipped with an outdoor reset control. Instead, provide controls and piping which can regulate the boiler re- turn water temperature at no less than 130°F regardless of system supply temperature. Contact your Weil-McLain representative for suggested piping and control methods.

Failure to prevent cold return water temperature to the boiler could cause corrosion damage to the sections or burners, resulting in possible severe personal injury, death or substantial property damage.

22

Part number 550-110-260/0107

Image 22
Contents Gold CGs How it works Gold CGs Gas-Fired Induced-Draft Water Boiler Contents Please read before proceeding InstallerUser Installations must follow these codes 1a Prepare boiler location codes & checklistBefore locating the boiler, check the following 1b Prepare boiler location clearances CGs special vent system When removing boiler from an existing common vent system1c Prepare boiler location vent system Vent system1d Prepare boiler location contamination Products to avoidSpecial considerations 1e Prepare boiler location air openingsCombustion air options Sizing air openingsSizing air openings for CGs installations Place boiler/crate near position 2a Prepare boiler placement & setupOrifice replacement procedure Inspect orifices and burnersDrain and remove fittings 2b Prepare boiler pressure testHydrostatic pressure test Prepare boiler for test3a Water piping general information 3b Water piping single-zone system Systems or converted gravity 3c Water piping multiple zonesPiping multiple zones Piping for radiant heating SystemsReturn water 130F or higher 3d Piping low temp systems Temperature gaugesValve adjustment Figures 8 and 9 only Primary/secondary preferred bypass piping methodPrimary/secondary piping Valve adjustment BOILER-bypass piping methodFigures 8 SYSTEM-bypass piping method 3e Water piping refrigeration systems Prevent chilled water from enteringVenting and combustion air Natural Gas Connecting gas supply piping to boilerGas piping Propane GasWiring connections Field wiringElectrical installation must comply with ThermostatCheck for gas leaks Freeze protection when used7a Start-up preparation Verify water chemistryFinal check before starting boiler 7b Start-up operate boilerInspect system water piping Inspect base insulation Start the boilerCheck for 7c Start-up if boiler doesn’t startCheck burner flames Pilot burner flame FigureCheck-out procedure checklist Installation and service certificate9a Operation sequence 9b Operation wiring diagrams Schematic wiring diagramLadder wiring diagram 9c Operating instructions CGs-3 to CGs-6 9c Operating instructions CGs-3 to CGs-6 9c Operating instructions CGs-3 to CGi-6 10a Service and maintenance schedule Verify Proper Operation After Servicing10b Service & maintenance annual start-up Inducer motor Burners, base and inlet air boxCondensate drain system Oiled-bearing circulators10b Service & maint. annual start-up Boiler relief valve Relief valve, typicalCleaning boiler heating surfaces Review with ownerBefore troubleshooting 11a Troubleshooting procedureCheck the following Check pressure switch setting 11b Troubleshooting air pressure switchAir pressure switch Troubleshooting air pressure readingControl indicator lights NON-LOCKOUT modes 11c Troubleshooting control moduleControl indicator lights Lockout modes Troubleshooting the control moduleControl module connections 11d Troubleshooting control module lights Chart 1 Troubleshooting Power light statusChart 2 Tstat Circ & Power lights flashing Chart 3 Press Switch & Power lights flashing Chart 4 Flame & Power lights flashing Item 8 , Does blower motor operate? Verify Sequence of operation, , 12a Replacement parts Section assembly Base Jacket Trim Controls12b Replacement parts section assembly Section assembly12c Replacement parts base Base assemblyDescription Weil-McLain Part number 12d Replacement parts jacket Jacket assemblyBoiler Model Weil-McLain part number 12e Replacement parts trim Part number12f Replacement parts controls Propane gas components13a Dimensions Dimensional drawing13b Ratings DOEHandling ceramic fiber and fiberglass materials Removal of Combustion Chamber Lining or Base Panels