Adjustable Legs for Leveling and Floor Clearance
3.3.3 Clearances
If the boiler is to be installed near combustible sur- faces, the minimum clearances shown in the table be- low must be maintained.
Failure to provide for the service access clearances, even with
The boiler must be installed in a space large in com- parison to the boiler as described in Section 6.3 of the National Fuel Gas Code, ANSI Z223.1, latest edition.
No pipes,
ducts, etc. C in this area.
Front of | A | B | Back of | |
Boiler | Boiler | |||
|
|
|
|
| D |
|
|
|
|
|
|
|
|
|
|
|
| D |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| ||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| ||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| ||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Minimum Clearances from Adjacent Walls, Ceiling, and Obstructions
Type of Surface | Dimensions (inches) | |||
|
|
|
|
|
| A | B | C† | D |
|
|
|
|
|
Combustible Surfaces | 30 | 24 | 30 | 24 |
|
|
|
|
|
30 | 24* | 30 | 24** | |
faces |
|
|
|
|
†"C" dimension includes clearance to remove the burner. Do not put pipes, ducts, etc. in this area above the boiler.
*CSA minimum. Actual clearance depends upon stacking requirements.
**Service access need be only on one side of a boiler or row of boilers. Boilers may be installed immedi- ately adjacent to each other. However,
In Canada: The boilers are approved for installation with zero clearance to combustible surfaces, but 24 inch service clearances are recommended.
3.4ELECTRICAL CONNECTIONS
All field wiring connections for power and control are in the rear service panel on the back of the boiler. Low voltage and high voltage terminal strips are indi- cated on the wiring diagram. The boiler power circuit