8.Before re-installing the burner, check the cleanliness of the heat exchanger and the condi- tion of the combustion chamber. If corrosion or leaks are noticed, (green or otherwise, please call the factory for assistance)

9.Install the burner and mixer core. Reconnect the pilot tube, main gas union, 4 burner hold down nuts, electrode wire, ground wire, mixer core tube, UV Scanner. Be sure the Pilot tube is not touching any other component.

5.3REMOVING THE EXCHANGER

1.Remove the burner as above.

2.Remove the front doors by pulling forward and upward.

3.Remove the top panel of the inner cabinet.

4.Close the isolation valves to the system.

5.Drain the boiler.

6.Disconnect the supply and return lines.

7.Remove the manifold assembly containing the temperature-pressure indicator, relief valve and the water flow switch (on the D series units dis- connect at the grooved pipe coupling [Victau- lic]).

Maintenance

8.Remove the nuts and bolts from the flanges of the inlet and outlet nozzles at the rear of the outer casing.

9.Remove the exchanger and clean the fins.

Note: The inner and outer cabinets are separate parts and reassembly is easier if the inner cabinet and exchanger are removed together as one unit.

WARNING!

The heat exchanger is heavy; use proper lifting equipment and techniques.

5.4AFTER ALL REPAIRS OR MAINTENANCE

1.Follow "Pre-Start Check List" (Section 3.10) and all "Safety Checks" (Section 3.11).

2.Check gas pressure and adjust gas flow if neces- sary. (See "Gas Pressure Adjustment", Section 3.12.3.)

3.Check air pressure and adjust air flow if neces- sary. (See "Air Flow Adjustment", Section 3.12.2.)

4.Perform combustion check.

26

Image 29
Contents PATTERSON-KELLEY Modu-FireGas-Fired Boiler Table of Contents What to do if you smell gas Modu-FireGas-Fired Boiler Introduction/SafetyBurn, Fire, and Explosion Hazards SafetyElectrical Hazards Chemical Hazards Modu-FireGas-Fired Boiler SafetyCrush Hazards Slip, Fall Hazards Modu-FireGas-Fired Boiler Safety Pressure HazardsInstallation Storage Prior to InstallationPlacement Initial InspectionClearances Modu-FireGas-Fired Boiler InstallationCombustion AIR Barometric Damper Vent ElbowsAutomatic Vent Damper Flue ConnectionRemoving an Existing Boiler Pipe Capacity for Natural Gas Piping Design Modu-FireGas-Fired Boiler Gas Supply Piping by InstallerGas Bleeds and Vents by Installer Boiler Inlet and Outlet Connections Boiler Water Piping by InstallerInspection Flushing and FillingWater Quality Test of Limit Controls Test of Ignition Safety SystemTest of Low Water Cut-off 12.1A Configuring the Local Controller Test of Low Gas Pressure SwitchTest of High Gas Pressure Switch For example, assume the following settings Configuration level Is pressed Table of Parameters Installation Air Flow Adjustments 12.1B Optional Remote ControlBasic Combustion Adjustment Procedure Control Panel Front Lighting ProceduresModu-FireGas-Fired Boiler Operation Emergency Shut Off Normal Shut Down ProceduresDaily Maintenance WeeklyMonthly During Operation Semi-AnnuallyAnnually MaintenancePilot Tube Ceramic Spider Ignition Electrode Standard Modulating IRI Modulating Modu-FireGas-Fired Boiler MaintenanceLoss of Power Do not Parts/Technical Support Table of Contents for this SectionCustomer Connections Customer Customer Input Analog Connections Customer Alarm Safety Flame Interlock Start 2 # Interlock Start 1 # Alarm Safety Flame Interlock Start 2 # Interlock Start 1 # Customer Connections Page Page Modu-Fire Gas-Fired Boiler Parts/Technical Support Main Assembly PartLocal Control Panel Modu-FireGas-Fired Boiler Parts/Technical Support No.Part Modu-FireGas-Fired Boiler Parts/Technical Support Gas TrainsStandard Gas Train 1500 IRI Gas Train IRI Gas Train 1500 No. Part Modu-FireGas-Fired Boiler Parts/Technical Support CabinetLimited Warranty Limited WarrantyMODU-FIREBOILER