IDEAL INDUSTRIES HE15, HE9, HE18, HE12 manual General Sealed System Requirements

Page 11

GENERAL

5 SEALED SYSTEM REQUIREMENTS

ecl6060

Non-return

valve

 

Automatic

 

 

air vent

 

 

Hosepipe

 

 

(disconnect

 

Hose unions

after filling)

 

 

 

 

Additional

 

 

stop valve

 

Temporary hose

 

 

(disconnect

Double check valve

Hose connector

after filling)

 

assembly

 

 

 

 

(note direction of flow)

 

Note.

The method of filling, refilling, topping up or flushing sealed primary hot water circuits from the mains via a temporary hose connection is only allowed if acceptable to the local water authority.

1.General

a.The installation must comply with the requirements of BS.6798 and BS.5449.

b.The installation should be designed to work with flow temperatures of up to 82oC.

c.All components of the system, including the heat exchanger of the indirect cylinder, must be suitable for a working pressure of 3 bar (45 lb/in2) and temperature of 110oC. Care should be taken in making all connections so that the risk of leakage is minimised.

2.Safety Valve

4.Expansion Vessel

a.A diaphragm type expansion vessel must be connected at a point close to the inlet side of the pump, the connecting pipe being not less than 15mm (1/2" nominal) size and not incorporating valves of any sort.

b.The vessel capacity must be adequate to accept the expansion of the system water when heated to 110oC (230oF)

c.The charge pressure must not be less than the static water head above the vessel The pressure attained in the system when heated to 110oC (230oF) should be at least 0.35 bar (5lb/in2) less than the lift pressure of the safety valve.

For guidance on vessel sizing refer to the table in Frame

6. For further details refer to BS.5449. For IE refer to the current edition of I.S. 813.

5.Cylinder

A spring loaded safety valve complying with the relevant requirements of BS.6759 must be fitted in the flow pipe, as close to the boiler as possible and with no intervening valve or restriction. The valve should have the following features:

a. A non-adjustable pre-set lift pressure not exceeding 3 bar (45 lb./in2)

b.A manual testing device.

c.Provision for connection of a discharge pipe. The valve or discharge pipe should be positioned so that the discharge of water or steam cannot create a hazard to the occupants of the premises or cause damage to electrical components and wiring.

3.Pressure Gauge

A pressure gauge covering at least the range 0-4 bar (0-60 lb./in2) must be fitted to the system. The gauge should be easily seen from the filling point and should preferably be connected at the same point as the expansion vessel.

The cylinder must be either of the indirect coil type or a direct cylinder fitted with an immersion calorifier which is suitable for operating on a gauge pressure of 0.35 bar (5lb./in2) in excess of the safety valve setting. Single feed indirect cylinders are not suitable for sealed systems.

6.Make-up Water

Provision must be made for replacing water loss from the system, either:

a.From a manually fitted make-up vessel with a readily visible water level. The vessel should be mounted at least 150mm (6") above the highest point of the system and be connected through a non-return valve to the system, fitted at least 300mm (12") below the make-up vessel on the return side of the domestic hot water cylinder or radiators.

b.Where access to a make-up vessel would be difficult by pre-pressurisation of the system. Refer to 'Filling.'

classic HE - Installation & Servicing

11

Image 11
Contents Installation and servicing Classic HE Installation & Servicing Document Amendments HE12 HE15 HE18 Key to symbolsGeneral General DataClassic HE Location of Boiler General IntroductionSafe Handling Optional Extra KitsSide and Rear Flue Installation from inside onlyGeneral Boiler Water Connections Boiler ClearancesBathrooms Flue InstallationCompartment Installations GAS SupplyWater Circulation System General TerminalAIR Supply Water TreatmentCondensate Drain Refer to Frames 38, 39 LOW Head InstallationsElectrical Supply Open Vent System Requirements Fully PumpedGeneral Sealed System Requirements Sealed System Requirements Boiler Assembly Exploded view InstallationPack B Contents Installation UnpackingUnpack and check the contents Pack a Contents Hardware Pack 1 ContentsSide Outlet Kit Product No Installation Packaging and Casing RemovalDetermining the Flue Length Pack Product NoPreparing the Wall Flue Assembly Exploded ViewWall Mounting Template Remove any burrs and remove the inner flue support ring Cutting the Flue wall thicknesses of 75 to 705mmCut to length X, refer to Frame Without Optional Flue finishing Kit Connecting the Flue to the BoilerWall Mounting Plate Mounting the BoilerFor wall thickness 270mm to 775mm Cutting the Flue For flue lengths 270 to 775mm only Fitting the Flue AssemblyFlues over 1 metre long Installation Mounting the BoilerFitting the KIT Flue Extension DuctsFlue Roof Flue KIT Contents / OptionsFlue Arrangement Installation Flue Terminal PositionTerminal Position Minimum Dimension Engagement in the final flue duct seal Installation Assembling the Roof Flue KITCondensate Drain Condensate Pipe Termination ConfigurationsGAS Connection Water ConnectionsCondensate Pipe Termination Configurations External Controls Electrical ConnectionsBlue Black Brown Grey Orange Thermostat Pink Installation Pictorial WiringMID Position Valve Pumped only ThermostatBlue Yellow/green Black Orange Brown Violet Red Pink White Installation TWO Spring Closed ValveFrost Protection Initial Lighting Installation Commissioning and TestingFitting the Boiler Casing See diagram A, Frame To gain access to the gas valveWater Circulating System Initial LightingGeneral Checks Handing OverDisconnect the electrical supply and turn off gas supply Servicing Servicing ScheduleBoiler Front Panel Removal Burner and AIR BOX RemovalCleaning the Recuperator Servicing Cleaning the FAN Assembly / the FluewaysCleaning the Burner and Pilot Assembly Replacement of Parts General Servicing Cleaning the SiphonReassembly GAS Pressure AdjustmentThermistor sensor lead Servicing Overheat Thermostat ReplacementOn/off switch Thermostat controlPull off the two electrical connections Servicing Limit Thermostat ReplacementFlue Protection Thermostat Replacement Pilot Burner ReplacementGAS Control Valve Replacement Servicing Ignition Electrode and Lead ReplacementMain Burner and Main Burner Injector Replacement Combustion Chamber Insulation Replacement Servicing FAN ReplacementAIR Pressure Switch APS Replacement Printed Circuit Board PCB ReplacementServicing Heat Exchanger ReplacementCasing Front Seal Replacement Servicing Siphon Replacement Finding Fault FindingGC Part No Description Qty Product No Short List of PartsShort List of Parts Short Parts List Installer Notification Guidelines GAS Boiler Commissioning Checklist Service 7 Date Service 1 DateService 3 Date Service 5 DateCertified Product Technical TrainingUsers guide Minimum Clearances SafetyElectricity Supply Important NotesTo Shut Down the Boiler Control of Water TemperatureCleaning MaintenancePoints for the Boiler User
Related manuals
Manual 60 pages 45.45 Kb

HE12, HE15, HE18, HE9 specifications

The IDEAL INDUSTRIES HE series, comprising the HE24, HE18, HE15, and HE12 models, represents a significant advancement in the field of electrical testing and measurement tools. These versatile testers stand out in professional environments for their high accuracy, user-friendly interfaces, and advanced features designed to enhance efficiency and reliability in electrical inspections.

The HE24 is the flagship model, boasting an extensive range of functionalities. It includes advanced digital multimeter capabilities, allowing for precise measurements of voltage, current, and resistance. Its True RMS feature ensures accurate readings, even with non-linear loads. The HE24 also incorporates advanced connectivity options, including Bluetooth technology, enabling users to transfer data wirelessly to smartphones or tablets for further analysis. The large, backlit display enhances visibility in various lighting conditions, making it an ideal tool for both indoor and outdoor use.

The HE18 model, while slightly more streamlined than the HE24, still offers robust capabilities. It features multiple testing modes, including continuity and diode testing, catering to a wide range of electrical tasks. The HE18 also utilizes a user-friendly interface, allowing technicians to navigate easily through various functions. Equipped with a protective rubber housing, this model is durable and built to withstand the rigors of frequent use on job sites.

The HE15 and HE12 models represent the compact, entry-level offerings in the HE series. Designed for the budget-conscious user, these models retain essential functionalities such as basic voltage and current measuring capabilities while prioritizing ease of use. The HE15 includes a simple LED indicator to signal when measurements are being taken, promoting straightforward operation. Additionally, the HE12 features a lightweight design, making it the perfect tool for on-the-go technicians.

All models in the IDEAL INDUSTRIES HE series are engineered with safety in mind, adhering to stringent international testing standards. They provide superior insulation resistance and a high degree of accuracy, mitigating the risks associated with electrical work. Furthermore, their IP-rated enclosures ensure protection against dust and moisture, enhancing longevity.

In conclusion, the IDEAL INDUSTRIES HE24, HE18, HE15, and HE12 series represent a comprehensive range of electrical testing tools that cater to professionals' varied needs. With their combination of advanced features, user-friendly designs, and safety compliance, these models are excellent choices for any electrical technician aiming for accuracy and efficiency in their work.