A.O. Smith HW 610 warranty Draft Hood, Vent Connection, Vent Pipe Installation

Page 15

Building materials must not come in contact with combustion products from stack or chimney, due to the degradating properties of flue products.

Flue products must have a minimum clearance of 4 feet (1.22m) horizontally from, and in no case above or below, unless a 4-foot (1.22m) horizontal distance is maintained, from electric meters, gas meters, regulators and relief equipment.

CAN/CSA B149.1, Installation Code specifies a 6 foot horizontal vent terminal clearance to gas and electric meters and relief devices (this clearance is specified as 4 feet in the U.S. under the National Fuel Gas Code, ANSI/Z223.1). Therefore instruction, which specifies compliance with the 4 foot clearance, as applies in the U.S. only, and the CAN/CSA B149.1 Installation Code applies in Canada.

1.DRAFT HOOD

The draft hood furnished with this boiler must be installed without alteration. Provision must be made if the boiler is installed in confined space or a small boiler room to accommodate draft hood spillage and avoid risks described above. The upper air opening called for in the AIR REQUIREMENTS section of this manual is for this purpose.

2.VENT CONNECTION

Size and install proper size vent pipe. Do not reduce pipe size to less than that of the draft hood outlet.

Horizontal runs of vent pipe shall be securely supported by adequately placed (approximately every 4 feet or 1 meter), non- combustible hangers and/or slip joints suitable for the weight and design of the materials employed to prevent sagging and to maintain a minimum upward slope of 1/4" (21mm/m) per foot from the boiler to the vent terminals, see Figure 8. Dampers or other obstructions must not be installed in the vent. Be sure that the vent pipe does not extend beyond the inside wall of the chimney.

VENT PIPE INSTALLATION

FIGURE 8.

Where a continuous or intermittent back draft is found to exist the cause must be determined and corrected. A special vent cap may be required. If the back draft cannot be corrected by the normal methods or if a suitable draft cannot be obtained, a blower type flue gas exhauster may be employed to ensure proper venting and correct combustion if permitted by local codes.

WARNING

FAILURE TO CORRECT BACK DRAFTS WILL CAUSE AIR CONTAMINATION AND UNSAFE CONDITIONS.

Vent connectors serving appliances vented by natural draft shall not be connected into any portion of mechanical draft systems operating under positive pressure.

3. CONNECTING BOILER TO A COMMON VENT

Do not connect the boiler to a common vent or chimney with solid fuel burning equipment. This practice is prohibited by many local building codes as is the practice of venting gas fired equipment to the duct work of ventilation systems.

Where a separate vent connection is not available and the vent pipe from the boiler must be connected to a common vent with oil burning equipment, the vent pipe should enter the common vent or chimney at a point ABOVE the flue pipe from the oil fired unit.

Where two or more appliances vent into a common vent connector or manifold, the area of the common vent or vent connector should at least equal the area of the largest vent connector plus 50% of the areas of the additional draft hood outlets.

When removing a boiler from a system with a common vent, use the following steps:

Be sure the other appliances connected to the common vent are not in operation.

Seal any unused openings in the common venting system.

Visually inspect the venting system for proper size and horizontal pitch and determine there is no blockage or restriction, leakage, corrosion and other deficiencies which could cause an unsafe condition.

WARNING

Ensure sufficient supply and ventilation air. Under no circumstances should the equipment room where the boiler is installed ever be under negative pressure. Insufficient air supply can interfere with combustion and ventilation of this boiler resulting in unsafe conditions.

Insofar as is practical, close all building doors and windows and all doors between the space in which the appliances remaining connected to the common venting system are located and other spaces of the building. Turn on clothes dryers and any appliance not connected to the common venting system. Turn on any exhaust fans, such as range hoods and bathroom exhausts, so they will operate at maximum speed. Close fireplace dampers.

Place in operation the appliance being inspected. Follow the lighting instructions. Adjust thermostat so appliance will operate continuously.

Test for spillage at the draft hood relief opening after five minutes of main burner operation. Use the flame of a match or candle.

After it has been determined that each appliance remaining connected to the common venting system properly vents when tested as outlined above, return doors, windows, exhaust fans, fireplace dampers and any other gas burning appliance to their previous conditions of use.

Any improper operation of the common venting system should be corrected so the installation conforms with the current edition of CAN/CSA B149.1 (current edition). When resizing any portion of the common venting system, the common venting system should be resized to approach the minimum size as determined using the appropriate tables in CAN/CSA B149.1.

15

Image 15
Contents Tennessee Waltz Parkway Ashland City, TN Models HW 300, 399, 420, 520, 610Important Definitions Safe INSTALLATION, USE and ServiceGeneral Safety Table of Contents Propane Natural Dimensions and Capacity Data27.7 33.3 Recovery CapacitiesHigh Altitude Installations IntroductionLIQUefied petroleum gas models Controls and Function GPM LPM Manual Reset High LimitHigh Limit Switch Safety Flow Switch Thermal BalancerSafety Relief Valves Tank Temperature Control Required Ability GeneralThermometers Drain Valve Not SuppliedUnconfined Space Confined Space S. InstallationsCanadian Installations AIR RequirementsLeveling Installation ClearancesTypical Boiler Installation VentingVent Connection Vent Pipe InstallationConnecting Boiler to a Common Vent Draft HoodVenting Sidewall Optional Power Vent System Multiple Vent TableVenting System Model HW-300 Boiler Combined Vent Sizing TablesONE Boiler Installed Independent of the Primary System System InstallationsConventional Installations LINEAR-TEMP InstallationsMinimum Branch Sizes to Boilers NO. Suggested Items for InstallationSchematic of the LINEAR-TEMPSYSTEM Boiler Inlet Outlet SizesGAS Connections Correct GAS Purging and SizingModel Rated Manifold Pressure Number Input Natural Propane ExampleSpecific Multiplier Gravity GAS Pressure RegulatorsWiring Connections WiringHW 300 thru 670. Natural and Propane GAS U.S. & Canada HW 300 toD. System Single Stage I.I.D. Honeywell GAS ValveLINEAR-TEMP Installations Boilers and Secondary Circulator are Controlled by Page MODELS, Jucntion BOX W/4 Terminals Canadian MODELS, Junction BOX W/6 TerminalsCanadian MODELS, Junction BOX W/6 Terminals Schematic MODELS, Junction BOX W/4 Terminals MODELS, Junction BOX W/4 Terminals USE this Table for Correct Pump and Water Pipe Size Wiring Figures 16 and 17 on Pages 24Piping Commercial Boiler with Vertical TankCommercial Boiler with Horizontal Tank Commercial Boiler with Vertical TANK, CER-TEMP Wiring Figures 21 to 27 on Pages 28 toHW-300 HW-399 HW-420 HW-520 Three HW-520s, HW-610s or HW-670s UP-FLOW Model USE this Table for Correct Pump and Water Pipe Size Main Burner Operation and START-UP InstructionsFilling the System Pilot and Main BurnerPilot Burner Electronic Ignition Checking and Adjusting the Input Consumption RateRefer to Operating at Full Input or Full Capacity Stage Main Burner Operation Flame Current Sensed For Your Safety Read Before Lighting URN Pilo T Firing VA LVE Counterclockwise SET T HE Thermostat to Lowwest SettingGeneral Maintenance Manual Reset High Limit Switch Continuity TestRelief Valve Internal Contaminants Cleaning and Flushing InstructionsPRE-TROUBLESHOOTING HOT Water Supply Boilers Preventive MaintenanceCER-TEMP 80 Recovery System Checkout Procedure TroubleshootingYES Is there excessive draft conditions that may cause pilot Burner ignition problems?Is ceramic insulator surrounding the electrode in good Condition not cracked or broken?MV & MV/PV? Replace pilot burner assembly OFF LED Status and TroubleshootingLocation of LEDs Flame LED Yellow Status LED GreenNo Call for Heat Not applicable None OFF Conditions and Exceptions Limited Warranty