A.O. Smith HW 610 warranty USE this Table for Correct Pump and Water Pipe Size

Page 38

THREE HW-520's, HW-610's OR HW-670's UP-FLOW MODEL COMMERCIAL BOILER WITH HORIZONTAL TANK, CER-TEMP 80

DANGER

TEMPERATURE SETTING SHOULD NOT EXCEED SAFE USE TEMPERATURE AT FIXTURES. SEE TANK TEMPERATURE CONTROL WARNING. IF HIGHER PREHEAT TEMPERATURES ARE NECESSARY TO OBTAIN ADEQUATE BOOSTER OUTPUT, ADD AN ANTI-SCALD VALVE FOR HOT WATER SUPPLIED TO FIXTURES.

IMPORTANT

THE INSTALLATION OF SAFETY FLOW SWITCH AS SHOWN IS REQUIRED TO PROTECT THE BOILER IN CASE OF WATER SERVICE INTERRUPTION OR CIRCULATOR FAILURE.

+PIPING AND FITTINGS BETWEEN GATE VALVES AND BOILERS SHOULD BE BRASS OR BRONZE. OTHER PIPING SHOULD CONFORM TO LOCAL CODES.

GATE VALVES ARE SHOWN FOR SERVICING BOILER. HOWEVER, LOCAL CODES SHALL GOVERN THEIR USAGE.

*PRESSURE RELIEF VALVE RATING SHOULD NOT EXCEED PRESSURE CAPACITY OF ANY COMPONENT IN THE SYSTEM.

**INSTALL THERMOMETER AND PRESSURE RELIEF IN OPENINGS PROVIDED ON HW-520, HW-610 & HW-670.

USE THIS TABLE FOR CORRECT

PUMP AND WATER PIPE SIZE

 

Minimum

B & G

 

Model

Pipe Size

*Armstrong

Number

(Inches)

Pump

Pump Size

 

 

 

Size

 

 

A

B

 

 

 

 

HW-520

2-1/2"

1-1/2"

2"

S-45 2-1/2"

HW-610/670

3"

1-1/2"

3" HD-3

S-46

* Assumes 50 equivalent feet of piping or less.

FIGURE 33.

WIRING - FIGURES 21 to 27 on

pages 28 to 32.

HEATERS SPACED 24" APART

INSTALL IN ACCORDANCE WITH ALL LOCAL CODES

38

Image 38
Contents Models HW 300, 399, 420, 520, 610 Tennessee Waltz Parkway Ashland City, TNSafe INSTALLATION, USE and Service Important DefinitionsGeneral Safety Table of Contents Dimensions and Capacity Data Propane NaturalRecovery Capacities 27.7 33.3LIQUefied petroleum gas models High Altitude InstallationsIntroduction Controls and Function Thermal Balancer Manual Reset High LimitHigh Limit Switch Safety Flow Switch GPM LPMSafety Relief Valves Tank Temperature Control Drain Valve Not Supplied GeneralThermometers Required AbilityAIR Requirements Confined Space S. InstallationsCanadian Installations Unconfined SpaceVenting Installation ClearancesTypical Boiler Installation LevelingDraft Hood Vent Pipe InstallationConnecting Boiler to a Common Vent Vent ConnectionVenting System Venting Sidewall Optional Power Vent SystemMultiple Vent Table Combined Vent Sizing Tables Model HW-300 BoilerLINEAR-TEMP Installations System InstallationsConventional Installations ONE Boiler Installed Independent of the Primary SystemBoiler Inlet Outlet Sizes NO. Suggested Items for InstallationSchematic of the LINEAR-TEMPSYSTEM Minimum Branch Sizes to BoilersGAS Connections Purging and Sizing Correct GASGAS Pressure Regulators ExampleSpecific Multiplier Gravity Model Rated Manifold Pressure Number Input Natural PropaneWiring Wiring ConnectionsSingle Stage I.I.D. Honeywell GAS Valve HW 300 toD. System HW 300 thru 670. Natural and Propane GAS U.S. & CanadaLINEAR-TEMP Installations Boilers and Secondary Circulator are Controlled by Page Canadian MODELS, Junction BOX W/6 Terminals MODELS, Jucntion BOX W/4 TerminalsCanadian MODELS, Junction BOX W/6 Terminals Schematic MODELS, Junction BOX W/4 Terminals MODELS, Junction BOX W/4 Terminals Commercial Boiler with Vertical Tank Wiring Figures 16 and 17 on Pages 24Piping USE this Table for Correct Pump and Water Pipe SizeCommercial Boiler with Horizontal Tank Wiring Figures 21 to 27 on Pages 28 to Commercial Boiler with Vertical TANK, CER-TEMPHW-300 HW-399 HW-420 HW-520 Three HW-520s, HW-610s or HW-670s UP-FLOW Model USE this Table for Correct Pump and Water Pipe Size Pilot and Main Burner Operation and START-UP InstructionsFilling the System Main BurnerPilot Burner Electronic Ignition Refer to Operating at Full Input or Full Capacity Checking and Adjusting the InputConsumption Rate Stage Main Burner Operation Flame Current Sensed For Your Safety Read Before Lighting SET T HE Thermostat to Lowwest Setting URN Pilo T Firing VA LVE CounterclockwiseRelief Valve General MaintenanceManual Reset High Limit Switch Continuity Test HOT Water Supply Boilers Preventive Maintenance Cleaning and Flushing InstructionsPRE-TROUBLESHOOTING Internal ContaminantsTroubleshooting CER-TEMP 80 Recovery System Checkout ProcedureYES Condition not cracked or broken? Burner ignition problems?Is ceramic insulator surrounding the electrode in good Is there excessive draft conditions that may cause pilotMV & MV/PV? Replace pilot burner assembly Status LED Green LED Status and TroubleshootingLocation of LEDs Flame LED Yellow OFFNo Call for Heat Not applicable None OFF Limited Warranty Conditions and Exceptions