A.O. Smith HW 610 NO. Suggested Items for Installation, Boiler Inlet Outlet Sizes, Expansion Tank

Page 19

NO. SUGGESTED ITEMS FOR INSTALLATION

Short pipe nipple and pair of boiler loop tees in piping

1between system supply and return. One set per each group of boilers.

2Boiler pipe loop. See piping sizing data.

3Boiler circulator. See pump sizing data.

4Thermometer.

5Theraltimeter.

6Plug cock to control flow rate.

7Safety flow switches. For interlock with other systems or instead of low water cutoff.

8Relief valve.

With one -300, -399 or -420 item 9 is - sensing element of remote control.

With a group of -300's, -399's or -420's, item 9 is - for 1st

9boiler, the sensing element as above. For additional boilers, install a 2nd limit control if required by local codes. With any -520, -610 or 670 boilers, install 2nd limit control here if

required by local code.

BOILER INLET - OUTLET SIZES

10HW-300 - 1-1/4", HW-399 - 1-1/2", HW-420 - 1-1/2", HW-520 & HW-610 - 2".

10HW-300 - 1-1/4", HW-399 - 1-1/2", HW-420 - 1-1/2", HW-520 & HW-670 - 2".

MINIMUM BRANCH SIZES TO BOILERS

HW-300 - 1-1/4" HW-520, 610 (Single boiler

11

HW-399 - 1-1/2"

per pump) 2"

 

HW-420 - 1-1/2"

 

 

HW-300 - 1-1/4"

HW-520, 670 (Single boiler

11

HW-399 - 1-1/2"

per pump) 2"

HW-420 - 1-1/2"

Flow control valve. Required only if flow rate of system

12primary is excessive for size of boiler branch tees or if chilled water main is above boilers.

13System supply temperature thermometer.

14Boiler headers for three (3) boilers can be larger than pipe loop, if desired, to aid in balancing.

The system flow rate is selected to give the desired system temperature drop - depending on the design criteria.

The boiler generator flow rates, on the other hand, should be selected to give the temperature rise through the generator that is both economical and offers the best generator efficiency.

The boiler temperature rise is normally between 100C and 200C (200F and 400F). The system temperature that will be introduced to the boiler (inlet temperature) plus the selected boiler temperature rise selected from PUMP AND PIPE SIZING DATA should not exceed the high limit control setting of 1150C (2400F).

There should be a relation of the minimum system load to the size boiler selected as the first firing or base boiler. This will stabilize operation during minimum load periods.

B.Commercial Boiler Replacements

Application of LINEAR-TEMP®to a commercial boiler replacement with an old multiple pump installation is an excellent way to modernize the system. The A. O. Smith boiler(s) should be installed on a pipe loop with a separate circulating pump selected from PUMP AND PIPE SIZING DATA TABLE.

Figure 12 shows a line drawing of how the system headers should be connected to the pipe loop installed with the replacement boiler(s). Make-up water connections and accessories are not shown.

SCHEMATIC OF THE LINEAR-TEMP®SYSTEM

FIGURE 12.

Supply and return headers of the old system should be connected to the boiler loop with a pair of tees set close together. The boiler loop pump and the boiler(s) should be wired to operate only when any of the system pumps are in operation. The number of zone pumps that may be in operation at any particular time will take their required flow rate out from the first tee in the boiler piping. This water will be circulated through the proper branches from the supply header to the zones calling for heat. The water will be brought back to the return header and then into the second tee in the boiler pipe loop. There will be no conflict between the boiler pump and the zone pumps when the two tees in the boiler loop are placed close together.

Normal use of flow control valves is required to prevent cross circulation of zones as with any multiple pump system. Flow control is not required on boiler circuit.

Attention should be given to balancing gas inputs and water flow rates. Large systems with multiple boilers should include main water temperature control (with or without outdoor reset) to stage the boilers on and off in relation to the load on the system.

3. WATER SUPPLY LINE

These boilers can be used ONLY in a forced circulation hot water heating system. Since most forced circulation systems will be of the closed type, install the water supply line as shown on piping diagrams, Figure 7 to 11 on pages 14 and 18.

Fast filling of large pipe, old radiator installations and pressure purging of series loop systems (where high pressures are not available) requires bypassing of the pressure reducing valve. Generally, pressure purging is not possible with a well pump system. High point air venting is essential.

If the system is of the open type, a pressure reducing valve will not be required as the water supply to the system will be controlled by a manually operated valve. An overhead surge tank is required.

4. EXPANSION TANK

CAUTION

A closed system will exist if a check valve (without bypass), pressure reducing valve (without bypass), or a water meter (without bypass) is installed in the cold water line between the water heater and street main (or well).

Excessive pressure may develop causing premature tank failure or intermittent relief valve operation. This is not a warranty failure. An expansion tank or a similar device may be required in the inlet supply line between the appliance and the meter or valve to compensate for the thermal expansion of water under supply pressure, see Figure 7 on page 14.

An air separator as shown in the piping diagrams is recommended especially for modern commercial hydronic systems.

19

Image 19
Contents Tennessee Waltz Parkway Ashland City, TN Models HW 300, 399, 420, 520, 610Important Definitions Safe INSTALLATION, USE and ServiceGeneral Safety Table of Contents Propane Natural Dimensions and Capacity Data27.7 33.3 Recovery CapacitiesIntroduction High Altitude InstallationsLIQUefied petroleum gas models Controls and Function GPM LPM Manual Reset High LimitHigh Limit Switch Safety Flow Switch Thermal BalancerSafety Relief Valves Tank Temperature Control Required Ability GeneralThermometers Drain Valve Not SuppliedUnconfined Space Confined Space S. InstallationsCanadian Installations AIR RequirementsLeveling Installation ClearancesTypical Boiler Installation VentingVent Connection Vent Pipe InstallationConnecting Boiler to a Common Vent Draft HoodMultiple Vent Table Venting Sidewall Optional Power Vent SystemVenting System Model HW-300 Boiler Combined Vent Sizing TablesONE Boiler Installed Independent of the Primary System System InstallationsConventional Installations LINEAR-TEMP InstallationsMinimum Branch Sizes to Boilers NO. Suggested Items for InstallationSchematic of the LINEAR-TEMPSYSTEM Boiler Inlet Outlet SizesGAS Connections Correct GAS Purging and SizingModel Rated Manifold Pressure Number Input Natural Propane ExampleSpecific Multiplier Gravity GAS Pressure RegulatorsWiring Connections WiringHW 300 thru 670. Natural and Propane GAS U.S. & Canada HW 300 toD. System Single Stage I.I.D. Honeywell GAS ValveLINEAR-TEMP Installations Boilers and Secondary Circulator are Controlled by Page MODELS, Jucntion BOX W/4 Terminals Canadian MODELS, Junction BOX W/6 TerminalsCanadian MODELS, Junction BOX W/6 Terminals Schematic MODELS, Junction BOX W/4 Terminals MODELS, Junction BOX W/4 Terminals USE this Table for Correct Pump and Water Pipe Size Wiring Figures 16 and 17 on Pages 24Piping Commercial Boiler with Vertical TankCommercial Boiler with Horizontal Tank Commercial Boiler with Vertical TANK, CER-TEMP Wiring Figures 21 to 27 on Pages 28 toHW-300 HW-399 HW-420 HW-520 Three HW-520s, HW-610s or HW-670s UP-FLOW Model USE this Table for Correct Pump and Water Pipe Size Main Burner Operation and START-UP InstructionsFilling the System Pilot and Main BurnerPilot Burner Electronic Ignition Consumption Rate Checking and Adjusting the InputRefer to Operating at Full Input or Full Capacity Stage Main Burner Operation Flame Current Sensed For Your Safety Read Before Lighting URN Pilo T Firing VA LVE Counterclockwise SET T HE Thermostat to Lowwest SettingManual Reset High Limit Switch Continuity Test General MaintenanceRelief Valve Internal Contaminants Cleaning and Flushing InstructionsPRE-TROUBLESHOOTING HOT Water Supply Boilers Preventive MaintenanceCER-TEMP 80 Recovery System Checkout Procedure TroubleshootingYES Is there excessive draft conditions that may cause pilot Burner ignition problems?Is ceramic insulator surrounding the electrode in good Condition not cracked or broken?MV & MV/PV? Replace pilot burner assembly OFF LED Status and TroubleshootingLocation of LEDs Flame LED Yellow Status LED GreenNo Call for Heat Not applicable None OFF Conditions and Exceptions Limited Warranty