Primary Piping

System Piping - Radiant Heating with Mixing Valve

Connect the PERFORMANCE PLUS to the system piping as shown with a radiant sys- tem using a thermostatic mixing valve as shown in Fig. 14 page 25. The primary / sec- ondary piping ensures sufficient return tem- perature to the PERFORMANCE PLUS.

personal injury, death or substantial property damage.

Size the system piping and circulator to pro- vide the flow needed for the radiant system.

To control the zone circulators reference Figure 34, page 45.

NOTICE

If the radiant system tubing contains no oxygen barrier, a stainless steel heat exchanger must be used. Failure to install a heat exchanger could lead to premature failure of the outer tank and void any warranty claim.

WARNING

Radiant heating system piping should include a means of regulating the boiler return water. The return water tempera- ture to the unit should be maintained at 130ºF or higher. Failure to prevent low return water temperature to the unit could cause premature failure of the unit and it’s burner system resulting in severe

NOTICE

To ensure adequate flow rate through the PERFORMANCE PLUS, maintain a minimum 1 inch diameter on the system piping connecting the unit to and from the primary / secondary connection.

System Piping - Multiple Units Installation

Use a balance manifold system as the pri- mary / secondary connection to the space heating piping as shown in Fig. 16 page 26.

Refer to Fig. 11 page 23 to install air elim- ination and expansion tank.

For the space heating piping refer to the applications mentioned in this manual or use recognized design methods.

22

Image 28
Contents For Your Safety PG PLUS-25/30/35/40 Gas Fired Combination HeatersTable of Contents Section VI Vent / Combustion AIR Installation Section V Primary PipingSection Viii Internal Wiring Section IX External WiringSection VII GAS Piping Section X START-UP PreparationSection XI START-UP Procedures Section XII Temperature LimitsSection Xiii CHECK-OUT Procedures Section XIV Installation RecordSection Xvii Replacement Parts Product SpecificationsProduct & Safety Information To Protect Against Excessive Temperature and Pressure Do not try to light any appliance What to do if YOU Smell GASHomeowner Operating Restrictions Pre-Installation Items Section I Pre-Installation Items Boiler ReplacementCode Compliance Determining Product LocationPre-Installation Items Residential Garage InstallationsCombustion Air and Venting Section II Combustion Air VentingMethods of Accessing Combustion Air Into a Space Combustion Air and VentingCombustion Air Requirements Air OpeningsOutdoor Combustion Air Equipment Located in Confined Spaces One Permanent Air InletCombination of Indoor and Outdoor Combustion Air Vent SystemRemoval of an Existing Boiler f rom a Common Vent System Hydrostatic Test Procedures Unit Preparation Section III Unit PreparationHandling Instructions Hydrostatic Pressure TestUnit Preparation Completion of Hydrostatic Test and DrainingDomestic Piping Section IV Domestic Piping Domestic Piping Multiple Units Installation Mixing Valve AssemblyDomestic Piping Diagrams TR/SMART Series ApplicationPerformance Plus With Recirculation Performance Plus with Storage Tank Primary Piping Section V Primary Piping Primary Piping Closet Zero Clearance ApplicationsSystem Piping Zone Circulators Sizing Primary PipingSystem Piping Radiant Heating with Mixing Valve Personal injury, death or substantial property damagePrimary Piping Near Appliance Piping Primary piping Zoning with Circulators Primary Piping Low Temperature Radiant System Primary Piping Venting and Combustion Air Installation Section VI Venting General RequirementsVenting and Combustion Air Installation Category IV Vent Termination ClearancesLocating the Combustion Air Inlet Multiple Vent TerminationsVenting Option Non Direct Vent / Vertical Venting Option Direct Vent / Vertical Venting Option Non-Direct Vent / HorizontalVenting Option Direct Vent / Horizontal Horizontal Wall Thimble KitVent Appliance Adapters Excessive Horizontal Vent RunsDetermining Piping Lengths Allowable Equivalent Length Combined Vent and Combustion Air Standard Horizontal Venting Installation Location of Air Inlet Termination Venting and Combustion Air Installation Section VII Gas Piping Recommended Gas Supply PipingPipe Sizing Natural Gas Natural GASNatural Gas Supply Pressure Requirements Pipe Sizing Propane Gas Propane GASPropane Gas Supply Pressure Requirements Internal Wiring Section Viii Internal Wiring Wiring must be N.E.C ClassInternal Wiring Factory Wiring SchematicFactory Internal Wiring External Wiring Section IX External Wiring Installation ComplianceOutdoor Temperature Limit Line Voltage ConnectionsExternal Wiring Multiple Zone Field Wiring Using Zone ValvesField wiring with zone circulators Typical Zone Relay Panel Wiring Section X Start Up Preparation Performance PlusFilling the Outer Primary Tank and System Check Low Water Cut-Off Device Air Shutter Settings Verify Correct Pressure SwitchCheck Thermostat Circuit Start-Up Procedures Final Checks Before Start-upPerformance Plus Start-up If Performance Plus Does Not Start CorrectlyFor Your Safety Read Before Lighting Following instructions must be followed exactly, a fire orOr loss of life Operating InstructionsNatural Gas Propane Temperature Limits Section XII Temperature Limits Recommended Secondary Thermostat SettingTemperature Limits Section XIII- Check-Out Procedures Section XIV Installation Record Section XV Maintenance Schedule Service TechnicianOwner Maintenance GeneralCheck the Surrounding Area Section XVI Maintenance ProceduresInspect the Burner Area Check Combustion/ Ventilation Air Openings Inspect Vent System and Combustion Air PipingCheck Domestic System Check Expansion TankCheck Temperature / Pressure Relief Valve Check Ignition Wiring and Ground WiringCheck Control Wiring Check Thermostat Limit SettingsCheck Combustion Levels Check Burner Flame Flame SignalReview With Owner Section Xvii Replacement Parts Jacket Components Control Panel Components Electrical Panel Components Burner Components Specifications Graph 1 Performance Plus Pressure Loss Primary Side TTP Brazed Plate Heat Exchangers Maxi-flo Pool and Spa Heat Exchangers