Gas Piping
SECTION VII - Gas Piping
Gas Supply Piping Connection
NOTICE
The gas supply piping must be installed in accordance to all applicable local, state and national codes and utility requirements.
1.Remove the burner jacket hood. Refer to Figure 27 to pipe gas supply to the burner.
a.Install a pipe union at the factory sup- plied gas nipple, for ease of service.
b.Install a manual shutoff valve in the gas supply piping as shown in Figure 27. For installations in Canada the installer must tag and identify the main shutoff valve.
c.Install a drip leg on the gas supply line prior to connecting to the PERFOR- MANCE PLUS gas train as shown in Figure 27.
2.Support the gas piping using hangers. Do not support the piping by the unit or its components.
3.Purge all air from the gas supply piping.
4.Before placing the PERFORMANCE PLUS into operation, check and test all connections for leaks.
Close the manual shutoff valve during any pressure test with less than 13”w.c..
Disconnect the PERFORMANCE PLUS and its gas valve from the gas supply piping during any pressure test greater than 13”w.c..
WARNING
Do not check for gas leaks with an open flame. Use a gas detection device or bub- ble test. Failure to check for gas leaks can cause severe personal injury, death or substantial property damage.
5.Use pipe dope compatible with natural and propane gases. Apply sparingly only to the male threads of pipe joints so that pipe dope does not block gas flow.
WARNING
Failure to apply pipe dope as detailed above can result in severe personal injury, death or substantial property damage.
WARNING
Use a
Fig. 27: Recommended Gas Supply Piping
37