Hearth and Home Technologies HUDBAY-FS owner manual Wood Screws

Page 16

Step 3.

To install the round support box/wall thimble cover in a flat ceiling, cut a 10 in. (254mm) square hole in the ceiling, centered on the hole drilled in Step 2. Frame the hole as shown in Figure 5.13.

CEILING JOISTS

FRAMING

ROUND CEILING

SUPPORT BOX/WALL

THIMBLE COVER

1-1/2 in. (38mm) LONG

WOOD SCREWS

Figure 5.13

Step 4.

Assemble the desired lengths of pipe and elbows necessary to reach from the appliance up through the round support box. Ensure that all pipe and elbow connections are in their fully twist-locked position. Assemble as instructed.

Step 5.

Cut a hole in the roof centered on the small drill hole placed in the roof in Step 2. The hole should be of sufficient size to meet the minimum requirements for clearance to combustibles, as specified. Continue to assemble lengths of pipe and elbows necessary to reach from the ceiling support box/wall thimble up through the roof line. Galvanized pipe and elbows may be utilized in the attic, as well as above the roofline. The galvanized finish is desirable above the roofline, due to its higher corrosion resistance.

NOTE:

(1) If an offset is necessary in the attic to avoid obstructions, it is important to support the vent pipe every 3 ft. (914mm) to avoid excessive stress on the elbows, and possible separation. Wall straps are available for this purpose, Figure 5.12, on page 15.

(2)Whenever possible, use 45° elbows, instead of 90° elbows. The 45° elbow offers less restriction to the flow of flue gases and intake air.

Step 6.

Slip the flashing over the pipe section(s) protruding through the roof. Secure the base of the flashing to the roof with roofing nails. Ensure the roofing material overlaps the top edge of the flashing as shown in Figure 5.14. Verify that the chimney is the required height above the roof. See roof pitch table, Figure 4.3 on page 8.

SHINGLES OVERLAP ON

TOP EDGE OF FLASHING

CAP AND STORM COLLAR NOT SHOWN FOR CLARITY

Figure 5.14

Step 7.

Continue to assemble pipe sections until the height of the vent (before adding the termination cap) meets the minimum code requirements as outlined in the current CAN/CGA-B149 Installation Codes (in Canada), the National Fuel Gas Code NFPA 54/ANSI Z223.1 (in USA), or local codes. Note that for steep roof pitches, the vent height must be increased. See Roof Pitch Table (Figure 4.3, on page 8). In high wind conditions, nearby trees adjoining rooflines, steep pitched roofs, and other similar factors can result in poor draft, or down drafting. In these cases increasing the vent height or switching to the high wind termination cap may solve this problem.

Step 8.

Slip the storm collar over the pipe, and push it down to the top of the flashing (Figure 5.15). Use non-hardening sealant above and below the joint between the storm collar and the pipe.

OPTIONAL HIGH WIND

TERMINATION CAP

SECURE FLASHING WITH

NON-HARDENING SEALANT

AND ROOFING NAILS

Figure 5.15

 

 

 

 

Page 16

Quadra-Fire • Hudson Bay • 7003-121 Rev. i

10/08

Image 16
Contents Do not Discard this Manual What to do if you smell gasDo Discardnot Welcome to the Quadra-Fire Family Table of Contents 1Listing and Code Approvals BELOW. Keep Clear of ALL Obstructions Requirements for the Commonwealth of MassachusettsManufacturer Requirements Design & Installation Considerations Tools will apply to every installationGetting Started Inspect Appliance & ComponentsSelecting Appliance Location Appliance Location and ClearancesClearances 4Termination Locations Vent Termination Minimum ClearancesAlcove Applications Vent Information Venting ComponentsUse of Elbows Measuring StandardsHow to Use the Vent Graph Vertical Distance from Appliance to to the 90 ElbowHorizontal Termination StepCenter Hole Line Wallcenter Thimbleline Fold Strap Here Sheet Metal Screw Direct Vent Pipe Vertical TerminationStep Wood Screws Twist-lock the vent cap and seal Cathedral Ceiling Class a Metal Chimney Existing Masonry Chimney Retro Connector Fuel Conversions Gas InformationConverting to LP Gas Valve Regulator Replacement Remove pilot hood and set asideGas Pressures PressureGas Connection Check for GAS LeaksRecommendation for Wire Connecting to the ApplianceStanding Pilot Ignition System Wiring Wire Size Max. LengthRED 28 711 MM ValveAppliance Setup AccessoriesDoor Crown Installation Remove Shipping MaterialsGrille Installation Brick Set InstallationPositioning the Logs 13 Log SetMineral Wool Blower Installation 23 Blower Wiring DiagramDamper Adjustment Shutter AdjustmentGlass Replacement Door Frame with Glass Assembly ReplacementBefore Lighting Appliance Operating InstructionsControls For Your Safety Read Before Lighting Lighting ApplianceInitial Break-in Procedure Frequently Asked QuestionsAfter Appliance is Lit Troubleshooting Symptom Possible Cause Corrective ActionBe Placed in this Opening Maintaining and Servicing Your Appliance After servicingMaintenance Tasks Inspect Necessary. USE Caution When CLEANING/HANDLING Ceramic BurnerAppliance Dimension Diagram Reference MaterialsVent Components Diagram SLP Series Vent ComponentsVent Components List MiscellaneousRD. Service Parts List Stocked At DepotValve Components Pedestal Components DepotDescription Serial # Part Number CONDITIONS, Exclusions & Limitation of Liability Limited Lifetime Warranty Serial Number Date Purchased Date Installed Dealer Telephone Hudson Bay Direct Vent Gas Appliance