Hearth and Home Technologies QV32B-A Install Metal Roof Flashing, Foot minimum in snow regions

Page 46

G. Install Metal Roof Flashing

See minimum vent heights for various pitched roofs (Figure 10.14) to determine the length of pipe to extend through the roof.

Slide the roof flashing over the pipe sections extending through the roof as shown in Figure 10.15.

 

 

HORIZONTAL

 

 

OVERHANG

2 FT.

20 INCHES MIN.

VERTICAL

MIN.

 

 

WALL

 

LOWEST

 

 

 

DISCHARGE

 

 

OPENING

 

GAS DIRECT VENT

 

 

TERMINATION CAP

 

 

 

 

X

 

 

12

 

 

ROOF PITCH

 

 

IS X/ 12

 

H (MIN.) - MINIMUM HEIGHT FROM ROOF

 

TO LOWEST DISCHARGE OPENING

Roof Pitch

 

H (Min.) Ft.

Flat to 6/12........................................1.0*

Over 6/12 to 7/12............................1.25*

Over 7/12 to 8/12..............................1.5*

Over 8/12 to 9/12..............................2.0*

Over 9/12 to 10/12............................. 2.5

Over 10/12 to 11/12 ......................... 3.25

Over 11/12 to 12/12 ........................... 4.0

Over 12/12 to 14/12........................... 5.0

Over 14/12 to 16/12........................... 6.0

Over 16/12 to 18/12........................... 7.0

Over 18/12 to 20/12........................... 7.5

Over 20/12 to 21/12........................... 8.0

* 3 foot minimum in snow regions

Figure 10.14 Minimum Height From Roof To Lowest Discharge

Opening

 

 

NOTICE: Failure to properly caulk the roof flashing and pipe seams may permit entry of water.

Caulk the gap between the roof flashing and the outside diameter of the pipe.

Caulk the perimeter of the flashing where it contacts the roof surface. See Figure 10.15.

Caulk the overlap seam of any exposed pipe sections that are located above the roof line.

CAULK

Figure 10.15

H. Assemble and Install Storm Collar

CAUTION! Risk of Cuts, Abrasions or Flying Debris. Wear protective gloves and safety glasses during instal- lation. Sheet metal edges are sharp.

Connect both halves of the storm collar with two screws (see Figure 10.16).

Wrap the storm collar around the exposed pipe section closest to the roof and align brackets. Insert a bolt (provided) through the brackets and tighten the nut to complete the storm collar assembly. Make sure the collar is tight against the pipe section.

Slide the assembled storm collar down the pipe section until it rests on the roof flashing (see Figure 10.17).

Caulk around the top of the storm collar (see Figure 10.18).

Figure 10.16 Assembling the Storm Collar

Figure 10.17 Assembling the Storm Collar Around the Pipe

46

Quadra-FireQV32B-A, QV36B-A2014-900 Rev. U • 1/12

Image 46
Contents What to do if you smell gas ModelsHOT Surfaces Congratulations Homeowner Reference InformationTable of Contents User GuideFinishing Appliance SetupTroubleshooting Reference MaterialsLimited Lifetime Warranty Limited Lifetime WarrantyWarranty Conditions Listing and Code Approvals Installation of Carbon Monoxide Detectors Requirements for the Commonwealth of MassachusettsOperating Instructions User Guide Gas Fireplace SafetyYour Fireplace Fan Kit optional Fixed Glass AssemblyRemote Controls, Wall Controls and Wall Switches Clear SpaceFinal inspection by Lighting Instructions Standing PilotWhat to do if YOU Smell GAS Issue Solutions Frequently Asked QuestionsAfter Fireplace is Lit Maintenance and Service Logs Maintenance Tasks-Qualified Service TechnicianGasket Seal and Glass Assembly Inspection FireboxGetting Started Typical Appliance SystemTools and Supplies Needed Design and Installation ConsiderationsInspect Appliance and Components Framing and Clearances Selecting Appliance LocationClearances Constructing the Appliance ChaseModels Combustible Mantels Mantel and Wall ProjectionsCombustible Mantel Legs or Wall Projections Vent Termination Minimum Clearances Termination LocationsOpening Covered Alcove Applications Minimum Clearances for TerminationVent Table Key Vent Information and DiagramsApproved Pipe Use of ElbowsUse of Flex Vent ClearanceTop Vent Horizontal Termination Venting with 1 elbow Propane Minimum MaximumVenting with 2 elbows NG Venting with 2 elbows Propane V1 Minimum H1 + H2 MaximumTop Vent Horizontal Termination Venting with 3 elbows NG Minimum + H 2 MaximumTop Vent Vertical Termination No Elbow = 60 ft. Max .3 m Exhaust restrictor InstructionsMinimum Maximum + V 2 Minimum Top Vent Vertical Termination Venting with 2 elbows NGTop Vent Vertical Termination Venting with 2 elbows Propane V1 Minimum H1 Maximum V1 + V2 MinimumTop Vent Vertical Termination Venting with 3 elbows NG Top Vent Vertical Termination Venting with 3 elbows PropaneTop Vent Vertical Termination Four 90º Elbows V1 Min H1 Max V2 Min H2 Max V3 MinH1 MAX V1 MIN H2 MAX H1 + H2 MAXH1 + H2 MAX H1 + H2+ H3 MAX Rear Vent Horizontal Termination Venting with 3 elbowsRear Vent Vertical Termination Venting with 1 elbow MIN MAXRear Vent Vertical Termination Venting with 3 elbows Rear Vent Vertical Termination Venting with 2 elbows+ H 2 MAX MIN Clearances to Combustibles Prior to installing the gas applianceCoaxial to Colinear Venting Termination Cap Flue DamperRear Vent Connecting the DV-46DVA-GCL Adapter to Appliance Top VentConnecting the LINK-DV30B to the DV-46DVA-GCL adapter MinimumWall Penetration Framing Vent Clearances and FramingPipe Clearances to Combustibles Combustible Wall PenetrationInstall the Ceiling Firestop Installing Ceiling FirestopFlat Ceiling Installation Install Attic Insulation ShieldVaulted Ceiling Installation Appliance Preparation Top VentRear Vent Cut the metal retaining band and fold the sides outSecuring and Leveling the Appliance 11 Proper Positioning and Securing of an ApplianceAssemble Vent Sections DVP Pipe Only Installing Vent Pipe DVP and SLP PipeAttach Vent to the Firebox Assembly Assemble Pipe SectionsAssemble Vent Sections SLP Pipe Only Assemble Slip SectionsSecure the Vent Sections Disassemble Vent SectionsInstall Decorative Ceiling Components SLP only Assemble and Install Storm Collar Install Metal Roof FlashingFoot minimum in snow regions Install Decorative Wall Components SLP only Install Vertical Termination CapHeat Shield Requirements for Horizontal Termination Install Horizontal Termination Cap DVP and SLP Pipe 20 Venting through the wallGas Pressure Gas InformationFuel Conversion Gas ConnectionOptional Accessories Requirements Wiring RequirementsElectrical Information Junction Box Installation Wall Switch Installation for Fan OptionalFinishing Facing Material NON-COMBUSTIBLE Board IncludedAppliance Setup Log Set Assembly LOGS-2014 Model QV32B-A Install the Log AssemblyLOG Install Hood Install the MeshInstall Trim and/or Surround Air Shutter SettingSymptom Possible Causes Corrective Action TroubleshootingStanding Pilot Ignition System Troubleshooting Symptom Possible Cause Corrective ActionReference Materials Appliance Dimension DiagramInches Millimeters Vent Components Diagrams Quadra-Fire QV32B-A, QV36B-A 2014-900 Rev. U 1/12DVP-TRAP DVP vent componentsDVP-TRAPFL RF6M RF12MBEK DVP-BEK2 COOL-ADD251 mm 222 mm 165 mm 165 mm9-1/4 235 mm 152 mm 168 mmElbow Elbow Effective Height LengthSLP-DCF-BK SLP-SNKD SLP-CCS-BKSL-2DVP SLP-WT-BKVent Components Diagrams Coaxial to Colinear Venting LINK-DV30B DV-46DVA-GCLAt Depot Service PartsLog Set Assembly Direct Vent Gas FireplaceSee valve assembly QV36B-A12.5 12.7 12.6 12.8 12.15 12.9 #12 Burner/Valve AssemblyPart number list on following 12.13Service Parts QV32B-A, QV36B-A StockedQV32B-A Conversion Kits QV36B-A Conversion KitsContact Information