Hearth and Home Technologies SL-750TRSFHHIPI Vent Information and Diagrams, Approved Pipe

Page 23

7 Vent Information and Diagrams

A. Approved Pipe

This appliance is approved for use with Hearth & Home Technologies DVP or SLP venting systems. Refer to Sec- tion 16B for vent component information.

DO NOT mix pipe, fittings or joining methods from differ- ent manufacturers.

The pipe is tested to be run inside an enclosed wall. There is no requirement for inspection openings at each joint within the wall.

WARNING! Risk of Fire or Asphyxiation. This appli- ance requires a separate vent. DO NOT vent to a pipe serving a separate solid fuel burning appliance.

B. Vent Table Key

The abbreviations listed in this vent table key are used in the vent diagrams.

Symbol

Description

 

 

V1

First section (closest to appliance) of vertical length

 

 

V2

Second section of vertical length

 

 

H1

First section (closest to appliance) of horizontal length

 

 

H2

Subsequent sections of horizontal length

 

 

C. Use of Elbows

Diagonal runs have both vertical and horizontal vent as- pects when calculating the effects. Use the rise for the vertical aspect and the run for the horizontal aspect (see Figure 7.1).

Two 45º elbows may be used in place of one 90º elbow. On 45º runs, one foot of diagonal is equal to 8-1/2 in. (216

mm)horizontal run and 8-1/2 in. (216 mm) vertical run. A length of straight pipe is allowed between two 45º elbows (see Figure 7.1).

Vertical in.1/2 -8

8-1/2 in.

Horizontal

Figure 7.1

D. Measuring Standards

Vertical and horizontal measurements listed in the vent diagrams were made using the following standards.

Pipe measurements are shown using the effective length of pipe (see Figure 7.2).

Horizontal terminations are measured to the outside mounting surface (flange of termination cap) (see Figure 6.4).

Vertical terminations are measured to bottom of termination cap.

Horizontal pipe installed level with no rise.

 

Pipe

Effective Length

 

Inches

Millimeters

 

 

 

DVP4

4

102

 

DVP6

6

152

Effective

DVP12

12

305

Height/Length

DVP24

24

610

 

 

DVP36

36

914

 

DVP48

48

1219

 

DVP6A

3 to 6

76 to 152

 

DVP12A

3 to 12

76 to 305

 

DVP12MI

3 to 12

76 to 305

 

DVP24MI

3 to 24

76 to 610

Figure 7.2 DVP Pipe Effective Length

 

 

Heat & Glo • SL-750TRSFHHIPI2156-900 Rev. F • 11/08

23

Image 23
Contents Hot glass will cause burns What to do if you smell gasHOT Surfaces Xxxxxxxx CongratulationsHomeowner Reference Information User Guide Table of ContentsReference Materials Appliance SetupTroubleshooting FinishingCONDITIONS, Exclusions & Limitation of Liability Limited Lifetime Warranty Listing and Code Approvals Requirements for the Commonwealth of Massachusetts Installation of Carbon Monoxide DetectorsYour Fireplace Gas Fireplace SafetyOperating Instructions User Guide Clear Space Fixed Glass AssemblyRemote Controls, Wall Controls and Wall Switches Fan Kit optionalGAS Valve Lighting Instructions IPIFinal inspection by What to do if YOU Smell GASAfter Fireplace is Lit Frequently Asked QuestionsIssue Solutions Remote Control Maintenance and ServiceMaintenance Tasks-Homeowner Glass CleaningLogs Maintenance Tasks-Qualified Service TechnicianGasket Seal and Glass Assembly Inspection VentingEither cobrahead or SIT Typical Appliance System Getting StartedAny such action may cause a fire hazard Design and Installation ConsiderationsTools and Supplies Needed Inspect Appliance and ComponentsSelecting Appliance Location Framing and ClearancesClearances Constructing the Appliance ChaseTOP View Mantel and Wall ProjectionsVent Termination Minimum Clearances Termination Locations= Vent Terminal = AIR Supply Inlet = Area Where Terminal is not PermittedUse of Elbows Vent Information and DiagramsApproved Pipe Vent Table KeyIn. Clearance Use of Flex VentMinimum Maximum SL-750TRSFHHIPI Top Vent Horizontal Termination Two ElbowsV1 Minimum H1 Maximum H1 + H2 Maximum V1 + V2 Minimum Top Vent Horizontal Termination Three ElbowsExhaust restrictor Instructions Top Vent Vertical Termination No Elbow = 60 ft. Max .3 mMinimum Maximum + V 2 Minimum Top Vent Vertical Termination Two 90º ElbowsH1+ H2 Maximum V1 + V2 Minimum Top Vent Vertical Termination Three 90º ElbowsV1 Min H1 Max V2 Min H2 Max V3 Min Top Vent Vertical Termination Four 90º ElbowsH1 Maximum V1 Minimum H1 + H2 Maximum H1 Maximum V1 Minimum H2+ H3 H1+ H2+ H3 Maximum Rear Vent Horizontal Termination Three ElbowsRear Vent Vertical Termination One Elbow H1 Maximum V1 Minimum H1 + H2 Rear Vent Vertical Termination Two ElbowsH1+ H2 Maximum V1 Minimum Combustible Wall Penetration Vent Clearances and FramingPipe Clearances to Combustibles Wall Penetration FramingPipe DVP SLP Install the Ceiling FirestopVaulted Ceiling Installation Install Attic Insulation ShieldFlat Ceiling Installation Top Vent Appliance PreparationCut the metal retaining band and fold the sides out Rear Vent13 Proper Positioning and Securing of an Appliance Securing and Leveling the ApplianceAssemble Pipe Sections Installing Vent Pipe DVP and SLP PipeAttach Vent to the Firebox Assembly Assemble Vent Sections DVP Pipe OnlyAssemble Slip Sections Assemble Vent Sections SLP Pipe OnlyDisassemble Vent Sections Secure the Vent SectionsInstall Decorative Ceiling Components SLP only Assemble and Install Storm Collar Install Metal Roof FlashingSLP-FS Install RF4-8Heat Shield Requirements for Horizontal Termination Install Vertical Termination CapInstall Decorative Wall Components SLP only Refer to of this manual Install Horizontal Termination Cap DVP and SLP PipeAnsi Z223.1 and CAN/CGA-B149 installation codes Gas Connection Gas InformationFuel Conversion Gas PressureElectrical Information Wiring RequirementsIntellifire Ignition System Wiring Optional Accessories RequirementsWith battery back-up Electrical Service and RepairWall Switch Installation for Fan Optional Junction Box InstallationSplatter Guard To install the Splatter GuardFinishing To Remove the Splatter Guard To Close the Lower Access Panel14 Wall Projection Acceptable on one side of opening 16 Facing Materials Facing MaterialTemplate DoorsElevated Hearth Systems Appliance Setup Step Install RefractoryStep LOG Notches Install the Log AssemblyNotch Air Shutter Setting Install Trim and/or SurroundIntellifire Ignition System TroubleshootingSymptom Possible Cause Corrective Action Ues to spark, and main Location Inches Millimeters Appliance Dimension DiagramReference Materials DVP vent components Vent Components DiagramsHorizontal Termination Cap DVP-TRAPDVP-TRAPFL RF6M RF12MBEK DVP-BEK2 COOL-ADDDVP-TV DVP-TB1 DVP-HRC-SS DVP-HRC-ZC-SS Horizontal Termination CAPSLP-HRC-SS SLP-HRC-ZC-SS Horizontal Termination CAP Roof Flashing Ceiling Firestop ElbowExtended Heat Shield RF4-8Adapter Snorkel Black Support Box-BlackWall Thimble-Black Service Parts Log Set AssemblyAt Depot Service Parts ListIPI Valve Assembly Contact Information