I. Install RF4-8

The RF4-8 may be used in place of the roof flashing and storm collar (Sections 10.G. and 10.H.)

Pipe must be supported within 12 inches of the roofline using plumbers strapping or an SLP-FS when using the RF4-8 Flashing. Refer to Section 10.D. Secure Vent Sections.

SECURE WITH 4

SCREWS NO LONGER

THAN 1 IN. (25 MM)

SLP-FS

Figure 10.18 Secure Pipe with SLP-FS

Trim the rubber boot (using scissors or a utility knife), cutting along the marked measurement lines. See Figure 10.19. Use the 150 mm line for SLP, 210 mm for DVP.

Lubricate pipe or flue with water and slide the flashing down. It may be necessary to trim the top shingles around the base of the rubber boot to ensure a good fit.

Draw a line around flashing. Remove flashing.

Apply silicone sealant to roof inside the lines (Figure 10.20).

Lubricate pipe or flue with water and slide flashing down. Seat firmly in sealant. Nail roof flashing to the roof.

Apply silicone sealant on the top and sides edges of the flashing. See Figure 10.21. Install shingles. Apply sealant at the top edge of the rubber boot. See Figure 10.22.

We recommend that you top coat with conventional acrylic house paint to improve the appearance of your galvanized base flashing.

Figure 10.20 Apply Sealant

APPLY SEALANT

TOP & PARTIAL SIDES

Figure 10.21 Slide Flashing Down, Secure & Apply Sealant

SILICONE SEALANT (TOP OF BOOT)

SHINGLES TRIMMED

FLASHING OVER

SHINGLES OVER

SHINGLES

FLASHING

 

Figure 10.22 Installation Complete

Figure 10.19 Trim Rubber Boot

46

Heat & Glo • SL-750TRSFHHIPI2156-900 Rev. F • 11/08

Image 46
Contents HOT Surfaces What to do if you smell gasHot glass will cause burns Homeowner Reference Information CongratulationsXxxxxxxx Table of Contents User GuideFinishing Appliance SetupTroubleshooting Reference MaterialsCONDITIONS, Exclusions & Limitation of Liability Limited Lifetime Warranty Listing and Code Approvals Installation of Carbon Monoxide Detectors Requirements for the Commonwealth of MassachusettsOperating Instructions User Guide Gas Fireplace SafetyYour Fireplace Fan Kit optional Fixed Glass AssemblyRemote Controls, Wall Controls and Wall Switches Clear SpaceWhat to do if YOU Smell GAS Lighting Instructions IPIFinal inspection by GAS ValveIssue Solutions Frequently Asked QuestionsAfter Fireplace is Lit Glass Cleaning Maintenance and ServiceMaintenance Tasks-Homeowner Remote ControlVenting Maintenance Tasks-Qualified Service TechnicianGasket Seal and Glass Assembly Inspection LogsEither cobrahead or SIT Getting Started Typical Appliance SystemInspect Appliance and Components Design and Installation ConsiderationsTools and Supplies Needed Any such action may cause a fire hazardFraming and Clearances Selecting Appliance LocationConstructing the Appliance Chase ClearancesMantel and Wall Projections TOP ViewTermination Locations Vent Termination Minimum Clearances= Area Where Terminal is not Permitted = Vent Terminal = AIR Supply InletVent Table Key Vent Information and DiagramsApproved Pipe Use of ElbowsUse of Flex Vent In. ClearanceMinimum Maximum Top Vent Horizontal Termination Two Elbows SL-750TRSFHHIPITop Vent Horizontal Termination Three Elbows V1 Minimum H1 Maximum H1 + H2 Maximum V1 + V2 MinimumTop Vent Vertical Termination No Elbow = 60 ft. Max .3 m Exhaust restrictor InstructionsTop Vent Vertical Termination Two 90º Elbows Minimum Maximum + V 2 MinimumTop Vent Vertical Termination Three 90º Elbows H1+ H2 Maximum V1 + V2 MinimumTop Vent Vertical Termination Four 90º Elbows V1 Min H1 Max V2 Min H2 Max V3 MinH1 Maximum V1 Minimum H1 + H2 Maximum Rear Vent Vertical Termination One Elbow Rear Vent Horizontal Termination Three ElbowsH1 Maximum V1 Minimum H2+ H3 H1+ H2+ H3 Maximum H1+ H2 Maximum V1 Minimum Rear Vent Vertical Termination Two ElbowsH1 Maximum V1 Minimum H1 + H2 Wall Penetration Framing Vent Clearances and FramingPipe Clearances to Combustibles Combustible Wall PenetrationInstall the Ceiling Firestop Pipe DVP SLPFlat Ceiling Installation Install Attic Insulation ShieldVaulted Ceiling Installation Appliance Preparation Top VentRear Vent Cut the metal retaining band and fold the sides outSecuring and Leveling the Appliance 13 Proper Positioning and Securing of an ApplianceAssemble Vent Sections DVP Pipe Only Installing Vent Pipe DVP and SLP PipeAttach Vent to the Firebox Assembly Assemble Pipe SectionsAssemble Vent Sections SLP Pipe Only Assemble Slip SectionsSecure the Vent Sections Disassemble Vent SectionsInstall Decorative Ceiling Components SLP only Install Metal Roof Flashing Assemble and Install Storm CollarInstall RF4-8 SLP-FSInstall Decorative Wall Components SLP only Install Vertical Termination CapHeat Shield Requirements for Horizontal Termination Ansi Z223.1 and CAN/CGA-B149 installation codes Install Horizontal Termination Cap DVP and SLP PipeRefer to of this manual Gas Pressure Gas InformationFuel Conversion Gas ConnectionOptional Accessories Requirements Wiring RequirementsIntellifire Ignition System Wiring Electrical InformationElectrical Service and Repair With battery back-upJunction Box Installation Wall Switch Installation for Fan OptionalFinishing To install the Splatter GuardSplatter Guard To Close the Lower Access Panel To Remove the Splatter Guard14 Wall Projection Acceptable on one side of opening Facing Material 16 Facing MaterialsDoors TemplateElevated Hearth Systems Appliance Setup Step Install RefractoryStep Install the Log Assembly LOG NotchesNotch Install Trim and/or Surround Air Shutter SettingSymptom Possible Cause Corrective Action TroubleshootingIntellifire Ignition System Ues to spark, and main Reference Materials Appliance Dimension DiagramLocation Inches Millimeters Vent Components Diagrams DVP vent componentsDVP-TRAP Horizontal Termination CapCOOL-ADD RF6M RF12MBEK DVP-BEK2 DVP-TRAPFLDVP-TV SLP-HRC-SS SLP-HRC-ZC-SS Horizontal Termination CAP DVP-HRC-SS DVP-HRC-ZC-SS Horizontal Termination CAPDVP-TB1 RF4-8 ElbowExtended Heat Shield Roof Flashing Ceiling FirestopWall Thimble-Black Snorkel Black Support Box-BlackAdapter Log Set Assembly Service PartsService Parts List At DepotIPI Valve Assembly Contact Information