VENT SYSTEM IDENTIFICATION
Installing Vent Components (Figure 36)
Begin the vent system installation by installing the first component, 90° elbow to the starting collars or straight pipe on the top of the appliance, then the straight pipe length and then horizontal or vertical termination kit.
NOTE: All outer connection joints must be sealed with aluminum tape, screws or silicone sealant rated above 300°F/149°C. The inner flue joints do not require any sealant.
Allventsystemcomponents lockintoplacebysliding theconcentric pipe section with four (4) equally spaced interior beads onto the appliance collar or previously installed component end with four
(4)equally spaced indented sections. When the internal beads of each starting outer pipe line up, rotate pipe section clockwise 90° (approximately 3 inches). The vent pipe is now locked together.
Continue adding components per the
| DV VENT KITS |
DV vent kit vertical, Flashing Kit w/Vertical Cap | |
DV vent kit top | |
DV vent kit rear | |
| DV vent kit top |
WALL THIMBLE
(MAXIMUM OF THREE 90 ELBOWS)
(MAXIMUM OF TWO 90 ELBOWS)
| Venting Components |
| Simpson |
Part Number | Description |
6" Pipe Length | |
9" Pipe Length | |
12" Pipe Length | |
24" Pipe Length | |
36" Pipe Length | |
48" Pipe Length | |
Adjustable Pipe Length 11 - 14 5/8" | |
Horizontal Square Termination Cap | |
Vinyl Siding Standoff | |
45° Elbow | |
90° Elbow | |
Wall Firestop | |
Ceiling Firestop | |
Roof Flashing - 0/12 to 6/12 Roof Pitch | |
Storm Collar | |
High Wind Vertical Top | |
36" Snorkel | |
14" Firestop Snorkel | |
Wall Thimble Firestop |
Figure 36
Page 22 |