6 Gas Information

A. Gas Pressure Requirements

B. Gas Connection

Pressure requirements for VRTIKL-CE Stoves are shown in Table 1 below.

Two taps are provided on the right hand side of the gas control for a test gauge connection to measure the inlet and outlet pressures. See Section 10: Maintaining and Servicing the Appliance.

The stove and its individual shut-off valve must be disconnected from the gas supply piping system during any pressure testing of the system at test pressures in excess of 60 mbar.

If the stove must be isolated from the gas supply piping system by closing an individual shut-off valve, it must be of the handle-less type.

WARNING

Fire Risk

Explosion Risk

High pressure will damage valve.

Disconnect gas supply piping BEFORE pressure testing gas line at test pressures above 60 mbar.

Close the manual shutoff valve BEFORE pressure testing gas line at test pressures equal to or less than 60 mbar.

Note: Have the gas supply line installed in accordance with local building codes by a qualified installer approved and/or licensed as required by the locality.

Note: Before the first firing of the stove, the gas supply line should be purged of any trapped air.

Note: Consult local building regulations to properly size the gas supply line leading to the (Rp 1/2 in.) hook-up at the unit.

Incoming gas line should be piped into the valve compartment and connected to the ISO 7-Rp 1/2 (BSP Rp 1/2 ) threaded gas inlet connection on the manual shutoff valve.

Leak test all gas line points and the gas control valve prior to and after starting the gas stove.

WARNING

CHECK FOR GAS LEAKS

Fire Risk

Explosion Risk

Asphyxiation Risk

Check all fittings and connections.

Do not use open flame.

After the gas line installation is complete, all connections must be tightened and checked for leaks with a commercially available, non-corrosive leak check solution. Be sure to rinse off all leak check solution following testing.

Fittings and connections may have loosened during shipping and handling.

Table 1

 

Natural Gas

Propane

Butane

Natural Gas

 

(G20)

(G31)

(G30)

(G25)

 

 

 

 

 

Inlet Pressure

20mbar

37 or 50mbar

30 or 50mbar

25mbar

 

 

 

 

 

Manifold Pressure

4-8.4mbar

15.7-25mbar

15.7-25mbar

4-8.4mbar

 

 

 

 

 

Gas Rate

.72 m3/h

.26 m3/h

.10 m3/h

.67 m3/h

Max.Input (NETCV)

6.9 kW

6.6 kW

5.8 kW

5.5 kW

 

 

 

 

 

Burner Injector

DMS 39

DMS 53

DMS 55

DMS 39

 

 

 

 

 

Pilot Injector

51

30

30

51

 

 

 

 

 

22

Heat & Glo • VRTIKL-CE7031-292 Rev E • 12/07

Image 22
Contents Do not Discard this Manual What to do if you smell gasDo Discardnot Test Lab Report No Manufactured Date Serial No Model NameTable of Contents Non-Combustible Materials 1Listing and Code ApprovalsAppliance Certification Combustible MaterialsGetting Started Design & Installation ConsiderationsInspect Appliance & Components Clearances to Combustibles 3Appliance Location and ClearancesSelecting Appliance Location 15.2 25.7 30.8 137.2 91.4 78.1 33.7 39.4Optional Stone Surround Installed 10.2 78.1 91.44Termination Locations Flue Termination Minimum ClearancesAlcove Applications Gas stoveUse of Elbows Flue InformationFlue Components Measuring StandardsFlueing Diagrams For Natural, Propane and Butane GasesNatural Gas One 90 0 Elbow System Natural Gas Two 90 0 Elbows System Min H1 Max H1 + H2 Max Natural Gas Two 900 Elbows System V1 Min Max Natural Gas Three 90 0 Elbows System Horizontal Termination StepSlim Line Wall Thimble Before YOU BeginFIG. B Minimum Clearance Vertical Termination Balance Flue PipeSecure Flashing with NON-HARDENING Sealant Roofing Nails Vertical Flue Restrictor Twist-lock the flue cap and sealGas Pressure Requirements Gas Connection Gas InformationCheck for GAS Leaks 7Electrical Information Ignition System WiringShock Risk Unbolting Appliance from the Pallet Appliance SetupRemove Shipping Materials Leveling and Bolting Down the ApplianceTop to Rear Flue Conversion AccessoriesOn TOP of Appliance Installing the Baffle On Back of AppliancePositioning the Logs Placing Mineral WoolCap and Barrel Fastener System Operating Instructions Before Lighting ApplianceLighting the Appliance Do not Connect 240 VAC to the Control ValveInitial Break-in Procedure Frequently Asked QuestionsAfter Appliance is Lit Maintaining and Servicing Appliance After servicingMaintenance Tasks Inspect Maintenance TasksSymptom Possible Causes Corrective Actions TroubleshootingElectronic Ignition System Reference Materials Appliance Dimension Diagram47.9 104.5 103.5 40.3 18.1 76.2 73.3 86.7 Appliance Dimension with Stone Surround Diagram 75.3 62.0 76.8 42.8 86.7 112.6Flue Components Diagram SL-09D SL-12/17D SL-24D SL-36D SL-48DComponents Flue Components ListTermination Kits Service Parts Log Set AssemblyDescription Serial # Part Number P2B/B2P-VRT-CEValve Assembly REM-DLX-CE Heat & GLO Limited 10 Year Warranty Warranty PolicyYour Records for Model Contact Information