1 OPERATION

OPERATING INSTRUCTIONS FOR RJ-88SC, RJ-100SC, & RJ-250SC 1-5

1. First, place the material to be discarded into the compactor.

Note: If you are loading the compactor through a door or gate, close it before starting the compactor. Refer to “Optional Loading Configurations” in the Decal Placement section to determine how your compactor is set up.

2.Insert the key into the key switch. Turn it clockwise and depress for 1 to 2 seconds and release. The unit will make one complete cycle, then stop.

3.Repeat, if necessary, after the compactor has stopped.

4.When you have finished using the compactor, remove the key from the key switch.

IN CASE OF EMERGENCY:

Push the large red button to STOP

MANUAL OVERRIDE INSTRUCTIONS (RAM STOP REAR ONLY - 88SC, 100SC, & 250SC)

If the ram is stopped in any position:

-To move the ram forward, turn the key switch clockwise and depress.

-To move the ram rearward, hold the reverse button down, turn and depress the key switch, release the key switch, then release the reverse button.

While the ram is moving:

-To reverse the ram while it is moving forward, press the reverse button.

-To cause the ram to move forward while it is moving rearward, depress the key switch.

NOTE: Refer to Optional Controls for Manual Override on Ram Stop Forward Machines.

Image 7
Contents Play IT Safe Contents Introduction OperationSide View SpecificationsWastec Only Authorized Personnel Should be Allowed Inside PRE-OPERATION InstructionsControl Description for 250VL Keyed Start Switch ReverseOperator Station Emergency Stop Control Description for 88SC, 100SC, & 250SCCase of Emergency Manual Override Instructions RAM Stop Rear only RJ-250VL Operating Instructions for RJ-250VLOptional Controls Decals for RJ-88SC, RJ-100SC, RJ-250SC, or RJ-250VL Remote Power Unit Security Chute Optional Loading ConfigurationsDock Access Gate & Hopper THRU-THE-WALLRear View Hydraulic Tailgate HT UnitsLOCK-OUT & TAG-OUT Instructions MaintenancePeriodic Maintenance Setting ProceduresPressure Setting Pressure Settings ReliefPrinte D Circuit Board Locate D I N Motor Control Panel RAM Control Timer AdjustmentRAM Stop Forward Option MULTI-CYCLE Timer Adjustment OptionWarranty and Service on Motors Cylinder Removal InstructionsPrinciples of Operation Standard System Operating CHARACTERISTICS, 5 hp & 10 hpSection A-A Tailgate Seal ReplacementFront View Door Seal on DoorTimer Settings ChartsFuses and Circuit Breakers Length Size Wire SizesPart Description Parts ListMotor Control Panel Typical Power Unit Standard 5 HP Power Unit Standard 10 HP Hydraulic Schematic Typical Problem Cause Solution TROUBLE-SHOOTING ChartPump Makes NOISE-SOUNDS Concrete PAD Concrete PAD RequirementsContainer Guides Decals Steel Installation ProceduresDock Installation CHUTE-FED InstallationRemote Power Pack Installation Electrical & Hydraulic InstallationElectrical Connections Pushbutton Operator StationSTART-UP Instructions Power Unit THROUGH-THE-WALL Power Unit InstallationTOP View Compactor See the Next page for Door and Latch Operation Instructions Hauler Instructions GeneralAuto Relatch Hauler Instructions DOOR/LATCH OperationLatch Side View Container For Optional HT Units Body Between the Tailgate and the Container Instructions for Using Maintenance BARHauler Instructions Liquid Removal For Optional SL Units