Xantrex Technology PV-30208 important safety instructions Section Installation and Initial TURN-ON

Page 12

SECTION 3

INSTALLATION AND INITIAL TURN-ON

The following wires for connecting the PV-30208 to external devices are not provided by Xantrex Technology: (See wiring diagram on page 3-6.)

3-Phase 208 VAC inverter output to terminals of the 208 VAC primary side of isolation trans- former. The neutral must be left floating. Ground loops will exist when the inverter starts switching, which will cause the inverter to shut down due to phase over-currents and will result in damage to the PV-30208. Also, insure that this neutral is not bonded to the isola- tion transformer frame.

System electrical ground to the isolation transformer chassis ground.

Isolation transformer grid side terminals to line circuit breaker (or the AC disconnect switch if present).

PV frame ground to PV-30208 enclosure chassis ground stud.

PV-30208 enclosure chassis ground stud to the electrical distribution system ground.

PV+ to the inverter enclosure terminal block TBDC+.

PV- to the inverter enclosure terminal block TBDC-.

PV neutral if connecting a bipolar PV array.

Install all wires listed above. Refer to the following wiring diagram and the system schematics in Section 7 for more detailed terminal locations.

DOCUMENT: 151315PV-30208 Photovoltaic Inverter3-5

Operation and Maintenance Manual

Copyright 2003, Xantrex Technology Inc.

Image 12
Contents South Vasco Road Copyright 2003, Xantrex Technology IncTable of Contents Section Product Description Introduction Major ComponentsMain Enclosure Section Product Description Interconnection Standards ComplianceMatrix Bus Board Solar Control Unit SCUSection Product Description Specifications Equipment SymbolSection Safety Safety Features Enclosure Front Access PanelPV Ground Fault Detection Section Safety Isolation Procedure Anti Island ProtectionTorque and Wire Gauge Specifications Utility Side Isolation Transformer RequirementsSection Installation and Initial TURN-ON Installation InstructionsInstallation Floor MountedSection Installation and Initial TURN-ON Ground Fault Detection Phase-SequencingArray Grounding Section Installation and Initial TURN-ON Wiring Diagram Optional Box Frame Optional PV Conductor PV Array Ground JumperPV-30208 Inverter Visual Inspection, PV Array Wiring Initial PowerVisual Inspection, Isolation Transformer WYE/WYE Visual Inspection, PV-30208Fine Tuning System VerificationSection Operation Description of System Operation OverviewOperating States Section Operation Operation Features Diagram Of Monopolar Configuration Section OperationBlock Peak Power Tracking Current Imbalance DetectionDC Overvoltage Detection Automatic Wake Up PV Voltage OptimizationSection Operation Operator Interface System Fault System Sleep Test System Stop System Shutdown Example of Normal System OperationSection Operation System Operating Parameters User Factory Password Parameter Description Section Operation Section Troubleshooting General Fault ConditionsFault Descriptions IPM Device Fault 0x0001 ThroughSection Troubleshooting AC Line Voltage Low FaultAC Line Voltage High Fault AC Line Under Frequency FaultAC Line Over Frequency Fault Ground Current FaultDC Bus Over Voltage Fault CT Offset FaultCurrent Imbalance Fault Stop Switch FaultSection Preventative Maintenance Periodic Maintenance Section Preventative Maintenance TURN-ON ProcedureSection Drawings and Parts List Drawings List Warranty and CertificationsOptional Accessories Page Page Page Page Page Enclosure, Upper Page Xantrex PV Series Limited Warranty and Registration