Xantrex Technology PV-30208 Section Operation Description of System Operation, Overview

Page 16

SECTION 4

OPERATION

DESCRIPTION OF SYSTEM OPERATION

Overview

The PV-30208 is a fully automated grid-tied photovoltaic inverter. Manual interaction or control of the inverter is necessary only in the event of a system fault. The following conditions govern PV-30208 operation:

Stable utility voltage and frequency must be present for all states of operation.

Fault states are automatic from any state of operation. A fault will cause the PV-30208 to immedi- ately stop processing all power. The fault condition will be reported to the operator interface.

The on/off switch, located on the upper enclosure of the PV-30208, must be switched to the on position for all operating states.

Cycling the on/off switch attempts to clear any system faults and return the PV-30208 to normal operation.

Operating States

Control software governs the operation of the PV-30208. There are six main operating states. The following descriptions depict the LCD interface. Line 1 (system status) of the LCD will indicate oper- ating states on the display.

Initializing: The LCD displays ‘Initializing’. The PCU monitors the status of the PV array and utility grid, waiting until the PV array voltage is sufficient to export power to the utility.

Wake-Up:The LCD displays ‘Wake Up Test’. Once the PV voltage is sufficient to export power to the utility grid, the PV-30208 will wait 5 minutes before starting. This insures the PV voltage is not transient in nature and keeps the system from cycling during unstable irradiance conditions.

Power Tracking: The LCD displays ‘Power Tracking’ while the PV-30208 delivers power to the utility. This is the standard operating state of the PV-30208. The PV-30208 maximum power tracker will optimize power output from the PV array. If available PV power is above the maximum power rating of the PV-30208, the inverter will current limit, which will cause the PV voltage to rise above the array peak power voltage. The minimum operating voltage of the PV-30208 is typically around 300 VDC. The power tracker will not track voltage below this point, regardless of the actual peak power voltage of the PV array.

Sleep Test: The LCD displays ‘Sleep Test’ while the control system begins a 5 minute sleep test. This normally indicates the PV irradiance is declining as the sun sets. If the output power remains below 200 watts during the 5 minute sleep test, the system will transition to standby. The time delay allows the inverter to ride through any temporary irradiance reductions.

Fault: The PV-30208 has encountered a fault condition. When this happens, regardless of the PV- 30208 state-of-operation, the PV-30208 will stop processing all power and execute an orderly sys- tem shutdown. Line 2 will display the fault description with the fault code displaying on line 3.

Shutdown: The LCD displays ‘Shutdown’. The PV array does not have enough power capacity to maintain the inverter operating losses or the line contactor is open and the devices are not switch- ing.

DOCUMENT: 151315

PV-30208 Photovoltaic Inverter

4-1

 

Operation and Maintenance Manual

 

Copyright 2003, Xantrex Technology

Image 16
Contents South Vasco Road Copyright 2003, Xantrex Technology IncTable of Contents Major Components Section Product Description IntroductionMain Enclosure Section Product Description Interconnection Standards ComplianceMatrix Bus Board Solar Control Unit SCUSection Product Description Specifications Equipment SymbolEnclosure Front Access Panel Section Safety Safety FeaturesPV Ground Fault Detection Section Safety Isolation Procedure Anti Island ProtectionTorque and Wire Gauge Specifications Utility Side Isolation Transformer RequirementsSection Installation and Initial TURN-ON Installation InstructionsInstallation Floor MountedSection Installation and Initial TURN-ON Phase-Sequencing Ground Fault DetectionArray Grounding Section Installation and Initial TURN-ON Frame Optional PV Conductor PV Array Ground Jumper Wiring Diagram Optional BoxPV-30208 Inverter Visual Inspection, PV Array Wiring Initial PowerVisual Inspection, Isolation Transformer WYE/WYE Visual Inspection, PV-30208Fine Tuning System VerificationOverview Section Operation Description of System OperationOperating States Section Operation Operation Features Section Operation Diagram Of Monopolar ConfigurationBlock Peak Power Tracking Current Imbalance DetectionDC Overvoltage Detection Automatic Wake Up PV Voltage OptimizationSection Operation Operator Interface System Fault System Sleep Test System Stop System Shutdown Example of Normal System OperationSection Operation System Operating Parameters User Factory Password Parameter Description Section Operation Section Troubleshooting General Fault ConditionsFault Descriptions IPM Device Fault 0x0001 ThroughSection Troubleshooting AC Line Voltage Low FaultAC Line Voltage High Fault AC Line Under Frequency FaultAC Line Over Frequency Fault Ground Current FaultDC Bus Over Voltage Fault CT Offset FaultCurrent Imbalance Fault Stop Switch FaultSection Preventative Maintenance Periodic Maintenance Section Preventative Maintenance TURN-ON ProcedureWarranty and Certifications Section Drawings and Parts List Drawings ListOptional Accessories Page Page Page Page Page Enclosure, Upper Page Xantrex PV Series Limited Warranty and Registration