SECTION 3
INSTALLATION AND INITIAL TURN-ON
ISOLATION TRANSFORMER REQUIREMENTS
The PV-30208 UL1741 certification requires the use of a Xantrex Technology specified 30 kVA WYE/ WYE isolation transformer between the inverter AC output and the utility interconnection (see Appen- dix in Section 7 for transformer dimensions and specifications). This custom 30 kVA isolation trans- former is not part of the 30 kVA inverter, but can be ordered as a separate item. If maintaining the listing to UL1741 is not a requirement for your application, contact Xantrex Technology for a fact sheet de- scribing the installation options and precautions for installing this inverter in a photovoltaic system that does not require UL1741 compliance.
WARNING
Xantrex Technology requires installing an isolation transformer between the PV- 30208 inverter and the point of utility interconnection. Failure to do so could result in catastrophic damage to the PV-30208 as well as the utility distribution system and will void the product warranty.
Inverter Side Isolation Transformer Requirements
The inverter side of the isolation transformer is configured as a WYE, and is rated for 208 VAC. The neutral connection on the inverter side must be left floating. If the neutral is tied to ground, the inverter will be damaged internally at power-up.
Utility Side Isolation Transformer Requirements
The utility-side windings of the isolation transformer are configured WYE and must match the voltage at the utility inter-tie. Verify that the transformer supplied matches the voltage requirement. Also, the transformer is supplied with a neutral connection on the utility side. Connection of this utility-side neutral does not affect the operation of the inverter. Check the local utility of jurisdiction for their requirements regarding the connection of this neutral.
Contact your Xantrex Technology distributor if you have any questions regarding isolation transformer requirements.
TORQUE AND WIRE GAUGE SPECIFICATIONS
The following torque specifications are to be used on all electrical interfaces made during installation of the PV-30208.
Torque Table
Terminal Block or Bolt Size | Torque Setting |
| |
5-16 Copper Lug | 52 in lbs./5.9 Nm |
| |
AC and DC Terminals | 275 in lbs/31.1 Nm |
| |
DOCUMENT: 151315PV-30208 Photovoltaic Inverter3-1
Operation and Maintenance Manual
Copyright 2003, Xantrex Technology Inc.