7.Now insert the trays into the side rack rails previously installed in the cabinet. If using, start first by inserting the external battery units. The UPS is inserted last. Make sure that the battery units are installed directly below the UPS.

Fig.5: Inserting the UPS (use same method for the battery units)

8. Now fasten the top cage nuts to the front post. If being used, screw the battery units to the rack. Insert the UPS loosely at first.

9. Check once again to make sure that the UPS and battery unit belong together.

EN

Never connect different voltage levels with one another!

Connect PROTECT D.1000 with PROTECT D.1000BP only!

Connect PROTECT D.1500 with PROTECT D.1500BP only!

Connect PROTECT D.2000 with PROTECT D.2030BP only!

Connect PROTECT D.3000 with PROTECT D.2030BP only!

10.Now follow the instructions provided in “Electrical Connection” in Chapter 6 on pg. 32 for the initial start-up.