AEG PV.500-MH manual 5.3.3Operation with Thin-FilmSolar Cells, General, Sequence control

Models: PV.500-MH

1 68
Download 68 pages 42.91 Kb
Page 35
Image 35
General:

Protect PV.500_MH Operating Instructions

5.3.2Operation With Monocrystalline or Polycrystalline Solar Cells

General:

This type of solar cell does not require active earthing.

Sequence control:

Insulation monitoring is always active.

Maintenance mode:

No action in the event of a "Maintenance mode" command.

Starting the insulation test manually:

No action, since the insulation test is always active.

5.3.3Operation with Thin-Film Solar Cells

General:

This type of solar cell requires active earthing.

Active earthing is switched on during the day and switches off at night. An insulation test is carried out at night.

When active earthing is switched on, the digital signals and ana- logue signal from the isometer are ignored.

Once active earthing is switched off, a certain time is allowed to elapse before the digital signals from the isometer are evaluated and the analogue measured value is output.

Sequence control:

When the equipment sequence control switches to the "Night" sta- tus (see Chapter 5.1.6), active earthing is switched off once a cer- tain time has elapsed.

The insulation test starts with a delay. Once a certain test time has elapsed, the insulation test finishes and active earthing is switched on again. If the sequence control switches to "Operation" status before the test time has elapsed, the timer control is ignored, the insulation test is terminated and active earthing is switched back on.

Maintenance mode:

Maintenance mode can be triggered either via a command or by means of remote signalling. Active earthing switches off immedi- ately when maintenance mode is activated. However, the digital and analogue signals from the isometer continue to be ignored.

Active earthing is switched on again the next time a switch is made to "Operation" status. However, the unit remains in maintenance mode for at least a certain time; i.e. even if the unit is switched over to the "Operation" status, maintenance mode is not terminat- ed until this time has elapsed.

Starting the insulation test manually:

The insulation test can be started manually for maintenance work.

Active earthing is switched off when the insulation test is started and the test actually commences once a delay has elapsed. When the test time has elapsed, the insulation test ends and active earth- ing is switched on again.

80000043212 BAL

35 of 68

Page 35
Image 35
AEG PV.500-MH manual 5.3.3Operation with Thin-FilmSolar Cells, General, Sequence control, Maintenance mode