External Connection

4.8.0.6 Installation of Batteries

See Installation Guide for Battery Cabinet for:

Preparing Batteries and UPS

Dimensions and Weight

Connecting Batteries

WARNING!

Before proceding, ensure that power supplies have been disconnected from UPS for a minimum of 5 minutes.

CAUTION!

Follow “Start-up Procedure” in APC Silcon User Guide.

Diagram - UPS with

 

 

Battery Cabinet

System Integration Interface

APC

 

 

 

 

UPS

 

 

Silcon

Battery Breaker trip for EPO

(Emergency Power Off)

Battery Cabinet

4.9Battery Breaker Box/Fuse-box

CAUTION!

Batteries connected to a UPS out of service for a period exceeding 8 days may be damaged. Refer to Section 7.0 Power Disconnection in this guide.

Battery Breaker Box/Fuse-box provides overcurrent and short-circuit protection for UPS installations with external batteries.

NOTICE!

If battery has been disconnected, refer to Section: - UPS Start Up in the APC Silcon User Guide.

990-4056

Installation Guide APC Silcon 240-320kW 400V UPS