System Operation

How to Apply Power to the System

1. Close (turn ON) the main circuit breaker of the power source supplying power to the PDU.

2. Close (turn ON) the Main Input on the PDU.

3.Power the PDU distribution circuit breakers.

For PDUs with transformer:

a. Close (turn ON) the Main Output circuit breaker on the PDU.

Note: After the Main Output circuit breaker has been closed, both PDU distribution panels will be energized.

For PDUs with and without a transformer:

b. Close (turn ON) the PDU distribution panel circuit breakers.

When the distribution panel circuit breakers are closed, the PDU power cables and connected equipment are energized.

Note

60kW InfraStruXure PDU—Operation and Configuration

29

Page 37
Image 37
American Power Conversion PD60H5HK1, PDRPPH1000 manual System Operation, How to Apply Power to the System