3.Select YES, Turn Load ON

Overview – The Display

Switch load ON.

1.From the Main Menu, select Control and press ENTER

2.Use UP/DOWN key to navigate to Turn Load ON, and press ENTER

3.Select YES, Turn Load ON

Switch into bypass.

1.From the Main Menu, select Control and press ENTER

2.Use UP/DOWN key to navigate to UPS into bypass and press ENTER

3.Use UP/DOWN key to navigate to YES, UPS into bypass, and press ENTER

Switch out of bypass.

1.From the Main Menu, select Control and press ENTER

2.Select UPS out of Bypass and press ENTER

3.Use UP/DOWN key to navigate to YES, UPS out of Byp, and press ENTER

Status views

Select Status on the Main Menu to view the status of the following parameters

Control

Logging

Status

Display

Setup

Diags

 

Help

Main Menu

Voltage on all phases.

Mains voltage (V), bypass voltage (V), and output voltage (V) for each phase.

Current on all phases.

Mains current (A), bypass current (A), and output current (A) for each phase.

kVA and kW.

Apparent power (kVA) and real power (kW) generated by the UPS to the load.

Frequencies.

Mains frequency, bypass frequency and output frequency in Hertz (Hz).

Load and batteries.

Load: Percentage of the load in relation to the total UPS capacity.

Bat Voltage: Shows either the positive or negative half of the battery voltage (the lower value of the two will appear).

Bat Cap: Percentage charge on the batteries in relation to the total battery capacity.

Runtime: The predicted runtime at the current load.

Batteries.

Bat AmpHr: Battery capacity, including both external and internal batteries.

UPS Temp: The highest external battery temperature.

990-2820A