American Power Conversion VT ISX manual Configuration, Connection of Load to the PDU

Models: VT ISX

1 36
Download 36 pages 25.44 Kb
Page 23
Image 23
Configuration

Configuration

Connection of Load to the PDU

Connecting load to the PDUs

Connect the load evenly between the 3 phases to avoid overloading one particular single phase. The total output capacity of the PDU is approximately twice the output capability of the UPS, meaning that the UPS would be over-loaded if all outlets were loaded to their

Note rating. Load status on the individual phases can be found through the UPS display or through the web interface.

Equipment connected to the 3-phased output may require overcurrent protection with a lower rating than the 3-phased output.

Note

For 3-phased outputs, the highest current may be in the Neutral conductor at non-linear loads (up to 173%).

Note

Connecting 1-phase load to PDU I

Connection of Load to the PDUConnecting load to the PDUs

 

 

 

 

 

 

 

 

 

 

 

 

Set the applicable breaker to the OFF position.

Guide the load cable down through the top hole.

Insert the plug from the load into the C19 outlet.

Secure the plug by inserting the locking brackets.

Set the applicable breaker to the ON position.

990-2820A

Smart-UPS® ISX 30-40 kVA, 400V Operation

17

Page 23
Image 23
American Power Conversion VT ISX manual Configuration, Connection of Load to the PDU, Connecting load to the PDUs