Configuration – Connection of Load to the PDU

Connecting 3-phase load to PDU II

 

 

 

 

1

1

 

 

 

 

 

Set the applicable breaker set to the OFF position.

Guide the load cable down through the top hole.

Lift up the receptacle cover and connect the load to the CEE 32A outlet.

Set the breaker set to the ON position.

Connecting 1-phase load to PDU II

1

 

 

1

 

 

 

Set the applicable breaker to the OFF position.

Guide the load cable down through the top hole.

Lift up the receptacle cover and connect the load to the CEE 16A outlet.

Reset the breaker to the ON position.