Maintenance (cont.)

Modular UPS with external maintenance bypass

(figure 31)

To service a number of modular UPSs with an external maintenance bypass, it is necessary to isolate them.

isolate the UPSs

Proceed in the following order:

shut down each inverter (press the "inverter off" button 7 for three seconds),

switch to the maintenance bypass whereby the load will be directly supplied by Mains 2 via Q3BP (close Q3BP, then open Q5 in the maintenance bypass cubicle),

open input switch Q4S on each UPS;

isolate each UPS from Mains 2 by opening the upstream protection devices,

open input switch Q1 on each UPS,

open output switch Q5N on each UPS.

The UPSs are de-energised (except the Mains 1 cables upstream of the Q1 switches on each UPS), but the load is supplied with Mains 2 power via the maintenance bypass. Complete isolation of the installation requires opening of the upstream protection devices on both Mains 1 and Mains 2.

start-up

Once servicing is completed, proceed in the following order:

close the input switches Q1 and Q4S on each UPS,

close output switch Q5N on each UPS,

close output switch Q5N in the maintenance bypass cubicle,

open switch Q3BP in the maintenance bypass cubicle,

close battery circuit breaker Q1 on each UPS,

External maintenance bypass

 

Q3BP

Modular UPS 1

 

Q4S

static switch

 

mains 2

 

rectifier-

inverter

charger

Q1

Q5N

mains 1

 

QF1

 

 

battery

Modular UPS 2

load

 

 

Q5N

Q4S

static switch

 

mains 2

 

rectifier-

inverter

charger

Q1

Q5N

mains 1

 

QF1

 

 

battery

Fig. 31

start all the inverters (press the

Note. It is strongly advised to call on

our after-sales support department for

"inverter on" button 6 ).

these operations.

The UPSs all come on line at the same

time if they are sufficient in number to

 

supply the load.

 

Frequency converter or parallel UPS with SSC

(figure 32)

During maintenance, the concerned UPS or converter must be isolated from Mains 1, its battery and the output circuits of the other units.

inverter isolation

Proceed in the following order:

shut down the inverter (press the "inverter off" button 7 for 3 seconds),

open isolating switches Q5N, QF1 and Q1 for that line.

The unit is powered down once the capacitors have discharged (a few minutes).

In redundant systems with at least one redundant UPS, the other UPSs (or converters) ensure continuity of power to the load.

Q1

mains 1

Q1

mains 1

Q1

mains 1

QF1

QF1

QF1

Q5N

Q5N

load

Q5N

Fig. 32: frequency converter exemple

Page 32 - 6739380EN/JC

Page 32
Image 32
APC 6739380EN/JC user manual Frequency converter or parallel UPS with SSC, Isolate the UPSs