50VQP

START-UP CHECKLIST

CUSTOMER:___________________________

JOB NAME: _______________________________________

MODEL NO.:___________________________

SERIAL NO.:____________________

DATE:_________

I.PRE-START-UP

DOES THE UNIT VOLTAGE CORRESPOND WITH THE SUPPLY VOLTAGE AVAILABLE? (Y/N)

HAVE THE POWER AND CONTROL WIRING CONNECTIONS BEEN MADE AND TERMINALS TIGHT? (Y/N)

HAVE WATER CONNECTIONS BEEN MADE AND IS FLUID AVAILABLE AT HEAT EXCHANGER? (Y/N)

HAS PUMP BEEN TURNED ON AND ARE ISOLATION VALVES OPEN? (Y/N)

HAS CONDENSATE CONNECTION BEEN MADE AND IS A TRAP INSTALLED? (Y/N) IS AN AIR FILTER INSTALLED? (Y/N)

II.START-UP

IS FAN OPERATING WHEN COMPRESSOR OPERATES? (Y/N)

IF 3-PHASE SCROLL COMPRESSOR IS PRESENT, VERIFY PROPER ROTATION PER INSTRUCTIONS. (Y/N)

UNIT VOLTAGE — COOLING OPERATION

PHASE AB VOLTS

PHASE BC VOLTS

 

 

PHASE CA VOLTS

 

 

(if 3 phase)

 

 

 

(if 3 phase)

PHASE AB AMPS

 

PHASE BC AMPS

 

 

 

PHASE CA AMPS

CONTROL VOLTAGE

(if 3 phase)

 

 

 

(if 3 phase)

 

 

 

 

 

 

 

IS CONTROL VOLTAGE ABOVE 21.6 VOLTS? (Y/N)

 

.

 

 

IF NOT, CHECK FOR PROPER TRANSFORMER CONNECTION.

TEMPERATURES

FILL IN THE ANALYSIS CHART ATTACHED.

COAXIAL HEAT

COOLING CYCLE:

 

C FLUID OUT

 

C

 

kPa

 

L/s

EXCHANGER

FLUID IN

 

 

 

 

 

HEATING CYCLE:

 

C FLUID OUT

 

C

 

kPa

 

L/s

 

FLUID IN

 

 

 

 

AIR COIL

COOLING CYCLE:

 

C

AIR OUT

 

C

 

 

 

 

 

AIR IN

 

 

 

 

 

 

 

HEATING CYCLE:

 

C

AIR OUT

 

C

 

 

 

 

 

AIR IN

 

 

 

 

 

 

 

Manufacturer reserves the right to discontinue, or change at any time, specifications or designs without notice and without incurring obligations.

Book

1

1

1

4

4

4

PC 111

Catalog No. 536-203

PrintedCL-1in U.S.A.

Form 62AQ-1SI

Pg CL-1

7-99

Replaces: New

Tab

1a

1b

5a

5a

6a

6b

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Page 47
Image 47
Carrier 50VQP084-300 50VQP START-UP Checklist, Ii. Start-Up, Book Catalog No, Form 62AQ-1SI Pg CL-1 Replaces New Tab