DLP- E145 Connect the PDU Ground Cables to the PDU
Note A shunt is preinstalled between logic and frame ground to bond the two grounds. If you are
providing a separate logic ground, remove this shunt on both sides before installing the PDU frame ground.
Figure 17-5 Power Terminal Block (Right Side Shown)
Step 2 Tighten the nuts to 36 in-lb.
Step 3 Repeat Steps 1 and 2 for the left side of the PDU.
Step 4 Replace the PDU safety covers.
Step 5 Return to your originating procedure (NTP).