PanelView Installation

OxyBalance Oxygen Display and Averaging System

Instruction Manual

IM-106-4050 Original Issue March 2006

PanelView Installation

This equipment is intended for use in clean, dry environments where only non-conductive pollution occurs (except occasionally a temporary conductivity caused by condensation), and with circuits not exceeding Over Voltage Category II (IEC 60664-1).

Disconnect all power before installing or replacing components. Failure to disconnect power may result in electrical shock and/or damage to the equipment.

Mounting Procedures

NOTE

If a communication module is ordered separately, make sure to attach the module to the base unit before panel installation. Refer to the PanelView Plus 600 manual for information on communication modules.

NOTE

Make sure the sealing gasket is properly positioned on the PanelView Plus 600. This gasket forms a compression seal. DO NOT use sealing compounds.

1.Insert the PanelView Plus 600 through the panel cutout on the front of the NEMA 4X protective enclosure front panel. Make sure to align the unit with the center of the panel cutout for adequate gasket sealing.

2.Insert the four mounting levers into the mounting slots on the unit, see Figure 5-3.Slide each lever until the flat side of the lever touches the surface of the panel.

3.Once all levers are in place, slide each lever an additional notch or two until you hear a click.

4.Rotate each lever in the direction indicated until it is in the final latch position.

5.Connect the power wires to the three wire contacts (L1, L2N, and ground) on the PanelView Plus 600. see Figure 5-1.

6.Connect the communication cord to the PanelView Plus 600.