19

3. Installation and start up

The power shelf must be installed on the framework and all AC, DC and control and alarm wiring must be connected before the rectifiers are physically plugged in.

Tools and test equipment

The following tools and test equipment are required:

Screwdriver, flat blade (3/8-inch)

Screwdriver, flat blade (3/32-inch)

Screwdriver, Burns No. 60, or equivalent

Cable strippers / electrician’s knife

Wire stripper

Cable cutters (2/0)

Linesman’s pliers

Open and box ended wrenches (set)

Socket set (1/2-inch drive)

Ratchet Wrench (1/2-inch drive)

Torque limiting torque wrench (1/2-inch drive)

Crimper, T & B 12 or 15 Ton head with 94H die

Digital Multimeter, Fluke 8000A or equivalent

Installing the power shelf

Installation of the power shelf consists of mounting the shelf in a cabinet or relay rack and connecting the AC, DC, and control and alarm connection cables.

Helios Rectifier 25/48NT5C06D Installation and User Manual

Page 19
Image 19
Emerson NT5C06D user manual Installation and start up, Tools and test equipment, Installing the power shelf