28 Installation and
Verification
After completing the wiring of the power shelf perform the following:
Procedure 2 - Verification
Step | Action |
1Verify that the power shelf has been mechanically secured.
2Verify that all the wiring performed is correct by using a voltmeter.
3Verify that all connections are mechanically correct (that is, tight, correct connector, correct marking etc.)
4Reinstall the AC and DC junction box cover on the left and right sides.
end -
Installing the rectifier
The NT5C06D rectifier is a
Procedure 3 - Rectifier installation procedure
Step | Action |
1 | Release the clamping bar by loosening the two captive screws |
2 | Remove the blank panel for the rectifier to be installed (place a finger in the |
| hole, lift up, pull forward, then lower to disengage upper tabs from the shelf |
| top). Store the panel at the bottom of the shelf, under the rectifier. |
3 | Ensure that both AC and DC circuit breakers are in the OFF position. |
4 | Use a voltmeter to verify that the AC supply at the input of the shelf is 208 |
| / 240 V AC nominal. |
5 | Carefully slide the rectifier in position on top of the stored blank panel. |
6 | Insure that the rectifier is firmly slid and seated into position. |
7 | Reinstall the clamping bar by securing the two captive screws. |
end
Factory setting
The rectifier is factory set as indicated in Table 7.
Table 7 - Rectifier settings
| Load | Slope load sharing method | |
| Sharing |
|
|
|
|
|
|
Rectifier Output Voltage (FLOAT) | 54.5 V DC | ± 0.1 | V |
Rectifier Output Voltage (EQUALIZE) | 55.2 V DC | ± 0.1 V | |
Rectifier High Voltage Shutdown (HVSD) | 59.0 V DC | ± 0.1 | V |
Rectifier Output Current Limit | 30 A | ± 0.5 | A |
UM5C06D (