20 Installation and
Procedure 1 - Installing the power shelf
Step | Action |
1 | Position the power shelf, without any rectifiers plugged in, against the |
| framework. |
|
|
2 | Secure the shelf in the position indicated by the job drawing (normally directly |
| below the controller or another shelf). At least one star washer must be |
| installed on one holding screw to ensure maximum framework ground |
| continuity. |
|
|
3 | Release the clamping bar from the front of the power shelf |
|
|
4 | Remove the AC and DC junction box cover, located on the left and right sides. |
| Store the parts for reinstallation after the wire connections have been |
| completed. |
|
|
| end |
Wiring the power shelf
Once the power shelf has been installed and firmly secured proceed with the wiring.
CAUTION
The power shelf wiring should be installed by qualified personnel and in accordance with the local electrical codes.
DANGER
Input voltage to the rectifier and the power shelf is at a hazardous potential. Ensure that the power switch is OFF at the AC service panel working on the power shelf. Hazardous voltages may still be present at the terminals even if the rectifiers are OFF. Use a voltmeter to verify the absence of voltage.
DANGER
Improper wiring can cause personal injury and equipment damage. Verify the proper polarity of the battery leads before connecting them to the power shelf, and clearly identify the positive and negative leads.
UM5C06D (