YSCFHC18G HIGH EFFICIENCY COOL ZONE SERIES GAS FRYERS
CHAPTER 3: INSTALLATION INSTRUCTIONS
3.3 Leveling the Fryer (cont.)
ANSI
NOTE: The installation must be inspected after it is complete to ensure it meets the intent of these instructions. The
For information on fryer restraints, see Section 2.8.
3.4 Gas Connections
The gas supply (service) line must be the same size or greater than the fryer inlet line. YSCFH18G gas fryers are equipped with a
Supply Line Specifications
The gas supply lines must be sized as indicated in the chart below, based on the total number of fryers connected to the main gas supply.
Recommended Gas Supply Line Sizes
Gas Types | Number of Fryers |
|
|
| 1 | 2 to 3 | 4 or more* |
Natural Gas | ¾" (22 mm) | 1" (28 mm) | 1¼ " (35 mm) |
Propane Gas | ½" (15 mm) | ¾" (22 mm) | 1" (28 mm) |
*When exceeding 18 feet (6 meters) for a configuration of more than four fryers, it is necessary to provide a 1¼" (35 mm) rigid gas connection.
DANGER
All connections must be sealed with a joint compound suitable for the gas being used and all connections must be tested with a solution of soapy water before lighting any pilots.
Never use matches, candles, or any other ignition source to check for leaks. If gas odors are detected, shut off the gas supply to the appliance at the main