Frymaster SM35 operation manual Pre-Installation cont, Equipment Installed at High Altitudes

Models: SM35

1 40
Download 40 pages 58 Kb
Page 14
Image 14
2.5 Pre-Installation (cont.)

DEAN MILLIVOLT GAS FRYERS (NON-CE)

CHAPTER 2: IMPORTANT INFORMATION

2.5 Pre-Installation (cont.)

C.Installation Standards

1.INSTALLATION STANDARDS: Fryer installation must conform with local codes, or in the absence of local codes, to the appropriate national standards as listed below:

 

a. U.S. installations must meet:

b. Canadian installations must meet:

 

American National Standard Institute

CAN 1-B149 Installation Codes

 

ANSI Z83.11

Canadian Gas Association

 

American Gas Association

55 Scarsdale Road

 

8501 E. Pleasant Valley Road

Don Mills, ONT, M3B 2R3

 

Cleveland, OH 44131

 

 

National Electrical Code

Canadian Electric Code c22.1, part 1

 

ANSI/NFPA #70

Canadian Standards Association

 

American National Standard Institute

178 Rexdale Blvd.

 

1430 Broadway

Rexdale, ONT, M9W 1R3

 

New York, NY 10018

 

 

NFPA Standards #96 and #211

 

 

National Fire Protection Association

 

 

470 Atlantic Avenue

 

 

Boston, MA 02110

 

 

 

 

D. Australian Requirements

 

To be installed in accordance with AS 5601 / AG 601, local authority, gas, electricity, and any other relevant statutory regulations.

2.6 Equipment Installed at High Altitudes

1.The fryer input rating [BTU/hr (kW/hr)] is for elevations up to 2,000 feet (610-m). For elevations above 2,000 feet (610-m), the rating should be reduced 4-percent for each additional 1,000 feet (305-m) above sea level.

2.The correct orifices are installed at the factory if the operating altitude is known at the time of the customer’s order.

2-4

Page 14
Image 14
Frymaster SM35 operation manual Pre-Installation cont, Equipment Installed at High Altitudes