Pump Assembly

Key:

Ref

P/N

Description

QTY

Ref

P/N

Description

QTY

1

106258

ORING, VIT, JCB

2

9

15K803

COLLAR, PUMP

2

2

108712

NUT, HEX, M8 X 1.25, MS

2

10

15K804

HOUSING, BEARING, SEAL, PR70S

2

3

120887

POSIPAK, 0.375ID X 0.625OD, COIL

2

11

15K824

SHAFT, PISTON, 3/8, PR70S, SS

2

4

120890

RING, RET, INT, 1.00, SS

2

12

15K828

WASHER, SEAL, 3/8, PR70S, SS

2

6

120982

SCREW, SHC, M8 X 1.25 X 65, MS, E

8

13

15K895

HOUSING, CHECK VALVE

2

7

15K786

HOUSING, PUMP, PR70S, MACHINED

1

14

LC0093

KIT, REBUILD, VALVE, CHECK, PR70S

2

8

15K787

CAP, END, PUMP, PR70S, MACHINED

2

 

 

 

 

To install a new Check Valve Rebuild Kit:

1.With the machine in an idle state and a bucket below the dispense valve to catch material, fully

extend the piston by pressing in the M1 screen.

2.To prevent machine movement, press (red).

3.With a bucket below the check valve to be replaced, disconnect the male hose fitting from the check valve housing (13), by loosing the hose from the housing. Catch any material draining from the hose into the bucket.

4.Remove the check valve housing (13) from the pump endcap (8) by loosening the housing with a wrench.

5.Remove the existing check valve (14) from the housing (13) by inserting a screwdriver or dowel rod into the female threaded end of the check valve housing.

6.With the new check valve ball guide (item #3 in figure 43) on a bench with the open end up, install the check valve spring (item 2 of figure 47) into the guide.

7.Install the check valve ball (item 1 of figure 47) on top of the spring.

8.With the rounded inside surface of the check valve seat (item 4 of figure 47) facing down, place the seat on top of the check valve ball.

9.Holding both ends of the assembled check valve assembly, install the check valve into the un-threaded end of the check housing (13) with the ball end facing out. Apply some pressure to the valve to snugly fit the completed check valve into the housing and the fit the check valve seat (item 4 of figure 47) into the valve guide.

10.Verify when the assembled check valve and housing (13) are turned up-side down, that the contents of the valve stays in place.

11.Re-insert the new valve and valve housing into the pump end cap, using a wrench.

12.Re-install the material male hose fitting into the check valve housing using a wrench.

13.Before re-using the machine for operation, activate a few shots to purge any air present in the material hose lines due to the procedure.

14.Re-calibrate the machine if necessary.

Figure 47: PR70 Check Valve Rebuild Kit (LC0093)

Key:

Ref

P/N

Description

QTY

Ref

P/N

Description

QTY

1

105445

BALL,CHECK VALVE

1

3

15D312

BUSHING, BALL GUIDE

1

2

121084

SPRING, 0.30OD X 0.44LG, 22#/IN, 20PSI, S

1

4

196832

SEAT, LAPPED, CHECK VALVE

1

312393G

36 of 50

Page 36
Image 36
Graco important safety instructions To install a new Check Valve Rebuild Kit, PR70 Check Valve Rebuild Kit LC0093 Key