ELECTRICAL POWER SUPPLY

2000 Autoflow

Autoflow to Fill System Control Box Interconnect

The Fill System Control Box houses the starter (s) for the fill system(s) that load grain into the Top Dry Autoflow Unit and for the aeration fan. DO NOT run the control wires for the Fill System Control Box in the same conduit used for the power wires for the fill system and aeration fan motors. To wire the Fill System Control to the Autoflow Control Box do the following.

1)Run ten (10) control wires from the Autoflow Control Box to the Fill System Control Box.

2)Connect the wires as shown in figure 24.

Figure 24

48

Page 48
Image 48
GSI Outdoors 2TFC, 2TAF installation instructions Electrical Power Supply, Autoflow to Fill System Control Box Interconnect