Heat & Glo • Soho-CE • 2111-900 Rev. D • 6/07 15
Combustible Wall Penetration
Frame a hole in a combustible wall for an interior wall
shield restop, (Figure 6.2) whenever a wall is penetrated.
Use same size framing materials as those used in the wall
construction. The wall shield restop maintains minimum
clearances and prevents cold air in ltration.
Non-Combustible Wall Penetration
If the hole being penetrated is surrounded by noncombustible
materials such as concrete, a hole with diameter 2.54 cm
greater than the pipe is acceptable.

B. Wall Penetration Framing

Figure 6.2 Exterior Wall Hole
A
B
25.4 cm
*Shows center of ue framing hole. The center of the
hole is one 2.54 cm above the center of the horizontal
ue pipe.
Fire Risk.
Explosion Risk.
Maintain ue clearance to combustibles as
speci ed.
Do not pack air space with insulation or other
materials.
Failure to keep insulation or other materials
away from ue pipe may cause re.
Figure 6.1 Pipe Clearances
7.62 cm TOP
CLEARANCE
2.54 cm CLEARANCE
AROUND VERTICAL
SECTIONS
2.54 cm SIDE AND
BOTTOM CLEARANCE
WARNING
A* B
96.5 cm 93.4 cm

A. Pipe Clearances to Combustibles

6
6 Flue Clearances and Framing