W A R N I N G

E q u i p m e n t C a b i n e t

N o t e

Installing the Switch

Installation Procedures

When the self test completes successfully:
The Power and Fan Status LEDs remain on.
The Fault and Test LEDs go off.

The port LEDs (includes the expansion module LEDs) go into their normal operational mode:

If the ports are connected to active network devices, the LEDs behave according to their function, Link or Activity.

If the ports are not connected to active network devices, the LEDs will stay off.

If the LED display is different than what is described above, especially if the Fault and Test LEDs stay on for more than 60 seconds or they start blinking, the self test has not completed correctly. Refer to chapter 4, “Troubleshooting” for diagnostic help.

3.After the self test has completed successfully disconnect the power cord in preparation for mounting the switch.

5. Mount the Switch

After the switch passes self test, you are ready to mount the switch in a stable location. The Series 6400cl Switch devices can be mounted in these ways:

in a rack or cabinet
on a horizontal surface
Rack or Cabinet Mounting

The Series 6400cl Switch devices are designed to be mounted in any EIA- standard 19-inch telco rack or communication equipment cabinet.

For safe operation, please read the installation precautions on page 2-4, before mounting a switch.

The 12-24 screws supplied with the switch are the correct threading for standard EIA/TIA open 19-inch racks. If you are installing the switch in an equipment cabinet such as a server cabinet, use the clips and screws that came with the cabinet in place of the 12-24 screws that are supplied with the switch.

Complete step 1, and plan which four holes you will be using in the cabinet and install all four clips. Then proceed to step 2.

Switch the Installing

2-11