The following is a general ordered list of tasks that are required to complete a Switch-Over migration:

Complete migration of a development environment, as discussed in the

In-place migration section.

Complete pre-migration steps required on production server

Backup production system

Perform pre-migration actions

Install WebSphere Commerce V5.6 components on the test server

Migrate instance

Backup database from the production server

Restore database to the test server

Run scripts to migrate database

Deploy migrated code from deployment machine

Complete required migration tasks on the test server

Test migrated instance

Take the WebSphere Commerce Suite V5.1 production server offline

Backup database from the production server

Restore database to the test server

Run scripts to migrate database

Chapter 3. Migration Strategy and Planning 47