Installation and Configuration Steps

2

Installation and Configuration Steps

Installation and configuration has several phases. In some cases, a separate person is responsible for each phase. It is important to coordinate the activities among the persons involved.

The customer or vendor installs the APs per the Configuration Guide for the AP being used. This is normally done before the SpectraLink 8000 Telephony Gateway installation, but should be done before step 3 below.

The first two steps are usually done by the customer up to the point of installing and connecting the SpectraLink 8000 Telephony Gateway(s) to the telephone demarc blocks and LAN access device. At that point, a qualified Polycom installer assists the customer in completing the remaining steps.

1.Site Preparation: Done by the customer or a wire technician/contractor.

2.SpectraLink 8000 Telephony Gateway Installation: Done by the customer or Polycom.

If five or more SpectraLink 8000 Telephony Gateways are to be installed, a SpectraLink 8000 SVP Server is required and would also be installed in this step.

3.SpectraLink 8000 Telephony Gateway Configuration: Done by the customer or Polycom.

Conditional:

SpectraLink 8000 SVP Server Configuration: If a SpectraLink 8000 SVP Server has been installed, its configuration would also be done in this step per SpectraLink 8000 SVP Server Administration Guide for SRP.

4.SpectraLink Wireless Telephone Configuration: Done by the customer or Polycom specialist per SpectraLink [model] Wireless Telephone Administration Guide.

5.System Certification: Done after installation to confirm the system is working properly per SpectraLink [model] Wireless Telephone Administration Guide.

PN: 1725-36028-001_T.doc

17

Page 17
Image 17
Polycom 1725-36028-001 manual Installation and Configuration Steps, Conditional