Powerware 6000 VA, 5000 manual EBM Installation, C A U T I O N

Models: 6000 VA 5000

1 66
Download 66 pages 55.12 Kb
Page 25
Image 25
EBM Installation

INSTALLATION

6.Align each joining bracket with the adjacent cabinet screw holes and secure with the supplied screws (see Figure 8).

7.If installing additional cabinets, repeat Step 6 for each cabinet.

UPS

Joining Bracket

EBM

Joining Bracket

Figure 8. Installing the Joining Brackets (Top View)

8.Continue to the following section, “EBM Installation.”

EBM Installation

C A U T I O N

A small amount of arcing may occur when connecting an EBM to the UPS. This is normal and will not harm personnel. Insert the EBM cable into the UPS battery connector quickly and firmly.

To install the optional EBM(s):

1.Verify that all battery circuit breakers are in the OFF (O) position (see Figure 9).

2.Plug the EBM cable of the first EBM into the UPS battery connector.

If additional EBMs are to be installed, plug the EBM cable of the second cabinet into the battery connector on the first EBM. Repeat for each additional EBM. Up to four EBMs may be connected to the UPS.

EATON Powerware® 9125 Two-in-One UPS (5000/6000 VA) User’s Guide S 164201513 Rev B

19

www.powerware.com

 

Page 25
Image 25
Powerware 6000 VA, 5000 manual EBM Installation, C A U T I O N