Chapter 3 Installing and Removing Server Switch Field Replaceable Units (FRUs)
Installing an InfiniBand Switch Module
Step 8 Tighten the screws on either side of the switch module to secure it to the chassis.
Figure 3-5 Securing an InfiniBand Switch Module
180744
Step 9 Verify that the system image on the InfiniBand switch module is consistent with the image on other cards in the chassis and update the image, if necessary. Use the show card command to determine the current image, as shown in the following example:
SFS-3012R# show card all
================================================================================
Card Information
================================================================================
admin | oper | admin | oper | oper |
slot type | type | status | status | code |
1* | controller | controller | up | up | normal |
7 | fc2port2G | fc2port2G | up | up | normal |
8 | fc2port2G | fc2port2G | up | up | normal |
14 | controller | controller | up | up | standby |
15 | ib12port4x | ib12port4x | up | down | |
16 | ib12port4x | ib12port4x | up | up | normal |
================================================================================
Card Boot Information
================================================================================Pr
boot | boot | boot |
slot stage | status | image |
1 | done | success | |
7 | done | success | |
8 | done | success | |
14 | done | success | |
15 | none | none | |
16 | done | success |
To interpret the output, examine the information for the slot in which you just installed the InfiniBand switch module. If the oper status is shown as “down” and the
See Chapter 4, “Viewing and Updating the Software Image” for instructions about updating the software image on the InfiniBand switch module.
Cisco SFS 3012R Multifabric Server Switch Hardware Installation Guide
|
| |
|